|
NSW GOVERNMENT - Transport for NSW Sydney Light Rail Public Private Partnership - Final Contract Summary: 25 Aug 2015Contents 1. Introduction 22. History and scope of the Sydney Light Rail project 23. Evaluation criteria and weightings used in tender process 54. Cost benefit analysis 65. Results of the public sector comparator 76. Public interest evaluation 87 . Risk sharing 9Overview of the Sydney Light Rail PPP 188 . Participants in the Sydney Light Rail PPP 189 . Contractual structure of the Sydney Light Rail PPP 2010 . Confidentiality and excluded material 2311. Auditor General's function 24Elements of the Sydney Light Rail PPP and related agreements 2412. Contract term and asset transfers 2413. Primary obligations 2514 . Activities of Transport for NSW and OpCo during the construction period 2515. Service de livery and quality requirements 2716 . Maintenance 2817 . Price 2918. Relief Events 3219. Compensation Events 3420 . Modifications and augmentations 3621. Defaults under the SLR Project Deed 3722. Termination rights 4023. Contractual remedies available to the Crown 4424. State step-in rights25. Transition out provisions 26. Transfer of land and assets by the public sector to the contractor27. Change of ownership and control under the SLR Project Deed28. Dispute resolution29 . Insurance30 . Liabilities, indemnities and guarantees given by the Crown31. Significant guarantees and undertakingsAppendix Appendix 1 Glossary of terms46 48 49 50 51 53 53 54 56 This report is a summary document and should not be relied upon for legal advice. This report is not intended for use as a substitute for the actual contracts.1. Introduction Th is report summarises the "Sydney Light Rail Project Deed" between:(a) Transport for NSW ABN 18 804 239 602 a New South Wales Government agency constituted by sect ion 3C of the Transport Administration Act 1988 (NSW); and( b) ALTRAC Light Rail Partnership, (OpCo), dated 17 December 2014 (SLR Project Deed).Th e SLR Project Deed is the main contract for the Sydney Light Rail Public Private Partnership (SLR PPP). The SLR PPP is a key component of the Sydney Light Rail project.Th is report has been prepared by Transport for NSW in accordance with the public disclosure requirements of the New South Wales Government's August 2012 NSW Public Private Partnerships Guidelines, and its compliance with these requirements was assessed by the NSW Auditor-General prior to its tabling in Parliament.This report should not be relied upon fo r legal advice and is not intended for use as a substitute for the contracts. This report is based on the contract as at 17 December 2014 as amended on 17 May 2015. Subsequent amendments of, or additions to, the contract are not reflected in this report.Th e defined terms used in this report are provided in a Glossary in Append ix A.2. History and scope of the Sydney Light Rail project NSW Government transport strategyIn Decembe r 2012 the NSW Government released two key strategic plans that set the framework for improving the central Sydney transport system - the NSW Long Term Transport Master Plan and Sydney's Light Rail Future - Expanding public transport, revitalising our city. The NSW Government has also released the Draft Metropolitan Strategy for Sydney 2031 that provides a comprehensive plan to manage growth of Sydney up to 2031.Sydney's Light Rail Future Sydney's Light Rail Fu ture outlines a four stage process to deliver new and improved light rai l services in Sydney as fo llows:(c) Stage 1 - Service integration and improvement: integration of light rail into MyZone ticketing and 131 500 information line and website (completed in June 2012) and introduction of the Opal card on light rail to make travelling easier between modes;(d) Stage 2 - Modernise and extend the existing network: construction of the 5.6 kilometre inner west extension to connect Dulwich Hill to the CBD (completed in March 2014), modern light rail fleet introduced to improve customer experience and real time information and timetable updates;(e) Stage 3 - Deliver a new CBD and south east service : overhaul of CBD bus network to integrate light rail and better connect commuters and completion of lightrail connecting Circular Quay, the CBD and south east Sydney including Moore Park and the University of NSW and the pedestrianisation of George Street between Hunter Street and Bathurst Street; and(f) Stage 4 - Longer term investigations: feasibility investigations of light rail or other high capacity public transport, like Bus Rapid Transit, for additional corridors including Victoria Road, Parramatta Road, Anzac Parade to Maroubra and potentially Western Sydney, continued support to counci ls investigating potential light rail schemes; growing the light rail network in line with demand and integrated with new urban development and investigating potential extensions to the line such as to Malabar, Walsh Bay and Barangaroo.To support and enable integration of light ra il into the CBD, a Sydney City Centre Access Strategy was also developed.Development of the CBD and south east Sydney light rail The new CSELR is an initiative being undertaken as part of a compr ehensive program toreform and improve Sydney's transport network. The key benef its of the CSELR are:(a ) unlocking of capacity in the CBD: it is estimated that, combined with a redesignof the bus network, approximately 220 fewer buses will be required in the CBD during the morning peak;(b) faster, more reliable and comfortable public transport: the serv ice will be a'turn up and go' service with new light rail vehicles for the CSELR (CSELRVs) thatpro vide a comfortable experience for customers. The CSELR will also be integratedwith the Opal tick eting system and provide modern and accessible stops with realtime service information;(c ) urban renewal and improved amenity: the CSELR will include a 1 kilometrepedestrianised zone along George Street between Hunter Street and Bathurst Streetwhich will su pport future urban renewal along the route; and( d) integration of the Sydney Light Rail: the CSELR will be integrated with the IWLR.Contract summa ry I Sydney Light Rail Project Page 3The Project The Project delivers:(a) conveniently located stops along the 12 kilometre route;( b) high frequency, 'turn up and go' services during peak periods;-- Inner West Ltghl Ra~1::::::::... Proposed stabling~ Propos4Xi m:JintenDOce faetl1ty0 Tra1n Interchange0 Major bus mterchange4) Ferry ~ntercharllje(c) additional special event services between Central Station and the Moore Park andRoyal Randwick Racecourse stops; ( d) major interchanges with ferry, heavy rail and bus services;(e) a fleet of electric-powered light rail vehicles (LRVs) with air conditioning andaccessible low-floor design;( f) a highly reliable service with the capability to fulfill the transport needs of this areafor the foreseeable future;( g) a pedestrian zone on George Street between Bathurst Street and Hunter Street;( h) wire-free operation between the intersection of George and Bathurst Streets andCircular Quay; ( i) public domain improvements including possible new public spaces, paving, trees,lighting and street furniture;C ontract summary 1 Sydney Light Rail Project Page 4(j) approximately 12 substations to provide power for the LRVs; and(k) a stabling facility in Randwick and a maintenance depot in Rozelle.The Sydney Light Rail PPP procurement process Following an extensive expression of interest evaluation process, the NSW Governmentannounced on 14 February 2014 that the following three consortia were short-listed tomove forward to the request for proposal stage for the SLR PPP. These consortia were:(a) Connecting Sydney - Transdev Sydney Pty Ltd, Alstom Transport Australia PtyLimited, Acciona Infrastructure Australia Pty Limited and Capella Capital Pty Limited;(b) SydneyConnect - Serco Australia Pty Limited, John Holland Pty Ltd and Plenary Origination Pty Ltd;(c) ilinQ Sydney - Keolis Australia Pty Ltd, Downer EDI Services Pty Ltd, BombardierTransportation Australia Pty Ltd, McConnell Dowell Constructors (Aust) Pty Ltd,Balfour Beatty Australia Pty Ltd and Macquarie Capital Group Limited.Transport for NSW released the request for proposal on 7 March 2014. On 11 July 2014,Connecting Sydney and SydneyConnect submitted proposals for the SLR PPP. ilinQ Sydneywithdrew from the process and did not submit a proposal.3. Evaluation criteria and weightings used in tender process The evaluation criteria which were used to evaluate the proposals are set out in the tablebelow. Table 1: Evaluation criteriaEvaluation criteria Number Description 1 Customer focussed outcomes during operationsThe extent to which the proponent's approach and operations solutions:• will deliver safe and sustainable high quality customer experienceoutcomes; • wi ll deliver effective stakeholder and community engagement; and• are compatible with the wider Transport for NSW network.2 Integrated design and optimised technical solutionsThe extent to which the proponent 's approach and design/technicalsolutions support the provision of a safe, integrated, proven, innovative,sustainable and high quality light ra il system that:• promotes customer e xperience;• enhances the urban environment; • provides capacity for project ridership demand; and• facilitates connectivity with the wider Transport for NSW network.3 Delivery solutionsThe extent to which the proponent's approach, including program and strategy:• provides delivery certaintt_ of the int~rated desl_g_n and qQtimisedEvaluation criteria Number Description technical solutions, including the integration of the IWLR;• demonst rat es:o a commitment to safety;o how the environmental and sustainability requirements willbe de livered; ando an understanding of effective stakeholder and communityenga gement;• demonst rates an efficient and effective means of achieving servicecomme ncement;• minimises disruption upon adj acent residents and businesses; and• effective ly manages impacts on the wider Transport for NSWnetwork a nd existing customers.4 Whole of life asset managementT he extent to which the proponent's approach and asset managementsolutions: • wi ll ensure assets are managed and maintained on a whole of lifebas is consistent with the design, technical and operationssol utions;• support the delivery of consistently high levels of performance; and• provide for assets to be handed back in an appropriate condition at the end of contract term.5 Commercial and financial acceptability to Transport for NSWTh e extent to which the proponent 's governance, legal and commercialst ructures are robust, sustainable and appropriate.The extent to which the proposal complies with the project agreements andthe acceptability and value for money impact of proposed departures.The extent to which the proponent's fund ing solution is robust andprovides the necessary security and fle~ibility to respond to SLR PPP risks.T he commitment of finance and the proponent's ability to achieve contractclose and financial close in accordance with Transport for NSW's timeframe.The financial strength of the proponent and its key risk-bearing entities.6 Risk-adjusted costThe extent to which the proponent's whole of life, risk-adjusted cost,t aking into account the financial risks and impacts to Transport for NSW,demonstra tes value for money.I n October 2014, following the evaluation of the proposals, Transport for NSW selectedConnecting Sydney (w hich subsequently changed its name to ALTRAC Light Rai l) as thepreferred proponent for the SLR PPP. Following final negotiations with ALTRAC Light Rai l,the SLR Project Deed was executed on 17 December 2014.4. Cost benefit analysis A business case for the project was prepared and a summary was published in November2 013. The business case provided a sound rationale for the SLR PPP by concluding theCSELR and associated bus network changes would achieve the project objectives,including: (a) improving reliability and efficiency of travel to, from and within the CBD and suburbsto the south east of Sydney;( b) improving access to major destinations in the south east of Sydney, including MoorePark , the University of NSW, Royal Randwick Racecourse and the Randwick healthprecinct ;(c) sa tisfying long term travel demand between the CBD and suburbs in south eastSydney; (d) increasing the use of sustainable transport modes in the CBD and suburbs in southeast Sydney; (e ) improving the overall amenity of public spaces in the CBD and suburbs in south eastSydney; and(f ) facilitating the continued, orderly and efficient growth of urban development andeco nomic activity within the CBD and suburbs in south east Sydney.The substantial net benefits of the project included:(a) customer benefits - providing faster, comfortable and more reliable journeys forp ublic transport users;(b) operating benefits - delivering a net saving in existing public transport operatingcosts; (c ) broader community benefits - generated through a reduction in environmentaland health costs (externalities) such as air pollution and noise; and(d) wider economic benefits - including sustainability benefits such as resourceefficiencies and additional greenhouse gas reductions associated with urbandensification and the benefits attributable to the va lue that people place on having anew high capacity , efficient, public transport service, even if they do not intend touse it regularly.The cost benefit analysis in the business case determined that the project would generate an et present va lue of $759 million and a benefit cost ratio of 1.4 excluding wider benefits,or a net present va lue of $973 million and a benefit cost ratio of 1.5 including wider benefits.5. Results of the public sector comparator The 'Public Sector Comparator' (PSC) provides a hypothetical estimate of the risk adjustedcost of the project if it were to be designed, built and operated by the State. To developthe estimate, the PSC was based on a reference project developed by the State, consistentwith the specified performance requirements.The PSC performs the following central roles :(a ) provides a benchmark for assessing the net present cost of t he private sector bids;(b) determines whether the State is receiving financial value for money derived from theprocurement of the project; and (c) ac ts as a key management tool during the procurement process.Cont ract summary 1 Sydney Light Rail Project Page 7The 'Raw PSC' is the base cost of delivering the project before any valuation of delivery and operating risks.The 'Risk Adjusted PSC' includes an adjustment for delivery and operating risks to betransferred under pri vate sector delivery. The value of itemised del ivery and operatingrisks was determined via statistical simulation using risk modelling software.The PSC used a discount rate of 5.54%, determined consistent with InfrastructureAustralia's National PPP Guidelines which specify the discount rate to be the relevantju risdiction's long-term borrowing rate, taken as the 10 year average of the 10 year NSWTreasury Corporation bond rate as advised by NSW Treasury at the commencement ofprocurement .Th e present value of the SLR PPP was evaluated using a discount rate that included asystematic risk premium of 1.35% for service payments and 1.15% for the conditionald ebt pay down, in accordance with NSW Treasury policies on the assessment of complyingproposals .Tabl e 2 provides a summary of the financial value for money analysis.Table 2 : Financial value for money comparison between public sector and private sectorproject deliveryCost category PSC ppp Difference Difference (NPC $m) (NPC $m) (NPC $m) (%) D&C costs' 1,185.1 1,389.7 204.6 17.3%O&M I Lifecycle 715.1 810.7 95.6 13.4%cost Total costs 1,900.2 2,200.4 300.2 15.8%Transferred risk 392.7 Included above - -Total NPC 2,292.9 2,200.4 (92.5) (4.0%)Th e comparison of the net present cost of the PSC versus the SLR PPP shows a benefit of$92.5 million or 4.0%.6. Public interest evaluation The public interest evaluation was init ially prepared during the development of the SLR PPPprocuremen t documentation. It was updated at several project milestones and finalised inOctober 2014. The evaluation considers each of the eight public interest criteria as set outin t he NSW Public Private Partnerships Guidelines 2012. These are:(a) effective ness in meeting government obj ectives;(b) achieving better value for money;1 For PSC, D&C and O&M/Lifecycle costs are shown on a raw basis (ie excluding risk adjustments)(c) community consultation; (d) consumer rights;(e) accountability and transparency;(f) public access;(g) health and safety; and(h) privacy. The public interest evaluation concluded that there were no significant issues identified thatwould preclude the public private partnership procurement for the SLR project.The Sydney Light Rail will result in positive benefits to the NSW economy, the community and stakeholders. The Sydney Light Rail is e xpected to deliver around $4 billion ineconomic benefits and provide frequent, fast, reliable light rail services that will improvetransport access to Central Station, the CBD and major destinations in south east Sydneyincluding Moore Park and the University of NSW.7. Risk sharing The risk sharing arrangement is in accordance with Infrastructure Australia's National PPPGuidelines. The State seeks to achieve best value for money by allocating risks to the partybest able to manage them. The risk allocation process results in various risks being:(a) retained by the State;( b) transferred to the private sector; or( c) shared between the parties.A structured approach to the ide ntification and analysis of potential risk and opportunitieson the project was undertaken, consistent with the Australian/New Zealand Standard forRisk Management AS/NZS IS031000. Comprehensive risk analysis was undertaken on the project which consisted of riskidentification, assessment , allocation and mitigation strategies. The Quantitative RiskAssessment (QRA) procedure undertaken was in accordance with the AustralianGovernment Department of Infrastructure and Transport "Best Practice Cost EstimationStandard for Publicly Funded Road and Rail Construction" updated May 2011. The QRAsimulation of itemised delivery and operating risks was determined via statisticalsimulation using risk modelling software . As discussed in section 5 (Results of the publicsector comparator) of this report, the results of the QRA model provides a numericalestimate of the overall effect of inherent uncertainty and contingent risk of the project,when considering risks, cost and schedule simultaneously. The SLR Project Deed and associated documents establish the obligations of each party inmanaging these risks. The risk sharing arrangements for the SLR PPP are summarised inTable 3.Table 3 : SLR PPP risk allocatione of Risk Additional landPlanning approvals Li cencesOther approvals Site availability Site conditions Information documents Remediation of contamination Pre-existing co ntaminationDescription Need to acquire rights to access and use landadditional to that made available to OpCoObtaining or modifying certain specified planningapprovals Delay in reaching completion due to legalchallenges to the planning approvals obtained byTransport for NSWDelays or additional costs to OpCo arising fromany modification to planning approvals requiredby OpCo after financial close The responsibility for complying with relevantplanning approval conditions (per the SLRProje ct Deed)The responsibility for obtaining licences underthe Protection of the Environment OperationsAct 1997 (NSW)Th e responsibility to obtain any other approvalsand the risk of additional costs and delay associated with them Responsibility to acquire agreed site and make it available to OpCo at the specified time duringth e construction of the SLR WorksGeotechnical and other site conditions in respectof the SLR Works Accuracy and completeness of information documentsManagement, containment and remediation ofcontamination caused or disturbed by OpCo's activitiesContainment and/or remediation of pre-existingcontamination caused by early works undertaken by Transport for NSW Containment and / or remediation of all other preexistingcontamination including that caused bylan d adjoining to OpCo's siteContainment and / or remediation ofcontamination as directed by an authority(outside of those areas managed by OpCo as apart of OpCo's activities)Type of Risk Native title claimsArtefacts Utility serv iceworks Temporary worksWHS I principalcontractor Community risksProperty noiseattenuation measures Description Paying compensation to native title holders or risk of delay to completionDiscovery of artefacts delaying completion and causing additional costsInvestigation, protection, relocation andmodification of utilities Provision of services/ utilities for constructionand operations by OpCoCompliance with utilities service agreements( incl. any treatment requirements)Temporary works installed are not suitable forthe purposes of the SLR Project DeedUndertake role of being the principal contractoron the site for WHS purposesE xceedance of noise and vibration limits,unacceptable traffic impacts/delays and otherdisruptions to the community during deliveryNoise attenuation measures to third partyproperties along the SLR siteDesign and Construction Dela ys in Time overruns on early works delayinghandover of early completion of the SLR Works worksSuitability of Early works are adequate and suitable for theearly works SLR WorksOpCo 's design Concept design does not meet the requirementsof delivery Phase or operations phaseDes ign interfaces Overall management of design interfaces (unlessrelating to an interface managed by Transport for NSW)Des ign review Compliance with design review process asoutlined in the SLR Project DeedConstruction Overall management of interfaces necessary tointerfaces deliver the SLR Works (noting the counterpartiesto the third party agreements will accept certainresponsibilities and risks)Site access Identification of sections within the networkf Risk Description Compliance with the agreed program of requiredaccess on a sec t ion by section basisCompl iance with the zone rental scheme whichrequires OpC o to pay a zone fee for the numberof days OpC o exceeds the agreed occupation periodTesting and Commissioning and CompletionSatisfyi ng Testing and commissioning not successfullyco mmissioning completed (for reaso ns other t han in relation toreq uirement s a risk borne by Tra nsport fo r NSW)Delays in Commissioning the SLR Works andcommissioning commencement of revenue serviceQuality Compliance of SLR Works with the requirementsset out in the S LR Project DeedDesig n and Design and co nstruction of t he SLR Works notconstruct ion completed on time or on budget (for reasonscompletion other than t hose in relation to a risk borne byTransport for NSW) State Inner West Light Rail ( existing infrastructure and IWLR Operations)Site access Responsibi lity to acquire site area agreed via ./S LR Project Deed and make it available to OpCoat the specified time for IWLR operationsDelays in obtaining accreditation to take overIWLR operations at the agreed timeService leve ls Achieving IWLR performance. requirements and service levelsOperations IWLR operations and maintenance (includingexisting staff) Infrastructure Di lapidation or wear of existing infrastructure ./Defects in existing infrastructure ./Information Accuracy and completeness of informationdocuments documents DDA compliance Complete Disability and Discrimination Act 1992 ./(Cth) compliance audit Ensure scope of work bid comp lies with theDisability and Discrimination Act 1992 (Cth)Op erational Risks (during full operations of SLR)Type of Risk Operational interfaces Meeting performance requi rements andservice levels Electricity supplyincluding interruption Adequacy of performance requirements and service levels Public transport information Ticketing systemSafety andsecurity Graffiti andva ndalism riskDescription Managing interfaces with third parties such asadjoining property owners, other transport providers and utilities Service solution or service performance does notmeet performance requirements and service levels specified by Transport for NSW (forreasons other than those in relat ion to a riskborne by Transport for NSW )In sufficient electricity supply availability duringthe operations phase to meet OpCo'srequirements (unless due to a specified relief event)Specified performance requirements and servicelevels will not be appropriate or sufficient tomeet Transport for NSW's requirements Provision of information for, and interface with,the Transport for NSW systemsProvision of, and performance risk relating to,electronic ticketing system and equipmentsupplied by Transport for NSWProvision of the legacy ticketing system from thedate of revenue service until the legacy ticketingsystem end date Ticket sales and ticketing responsibilitiesProvision of power and communications for thee lectronic ticketing system components andperformance of any specified functionsSafety and security of the Sydney Light Railsystem and its customers and staff (to theextent specified in the SLR Project Deed andunder rail safety legislation excluding lawenforcement functions) Responsibility for cost and disruptions caused bygraffiti or vandalism during constructionResponsibility for cost and disruptions toservices caused by graffiti or vandalism withinareas managed by OpCoResponsibility to remove or remediate graffitiand vandalismType of Risk Branding and mar ketingStop andinter changemanagement Disruptio ns topassenger service C ustomer ands top KPisDescription Responsibility for cost and disruptions toser vices caused by graffiti or v andalism outsideareas managed by OpCoContro l of branding and marketing activitiesConfo rmance with Transport for NSW brandingrequirements and meeting specificr esponsibilitiesCo ntrol and management of stops andinterchanges (within specified boundaries),in cluding all responsibility for asset availability,asset management, operations and cost riskDisruptions to passenger services during theoperations phase (for reasons other than thosein r elation to a risk borne by Transport for NSW)M eeting required standards with respect toc ustomer and stop management KPisAsset Management Asset information Responsibility for the Sydney Light Rail assetsystem information systemMaint enance Cost of maintenance and performance of assetsp erformance and relative to the SLR Project Deed requirements costAsse t condition Required asset condition standards are notthrough achieved through the operations phase.operatio ns phaseR esidual life and Satisfying Transport for NSW's requirements fore nd of term asset condition (IWLR and CSELR) 9nd residualh and over design life at the end of the co ntract termDefect - Early A defect in early works causes OpCo to incurWorks increased cos ts or results in an event whichtriggers abatement of the Service PaymentRevenue and Costs Reve nue Provision of fare enforcement functions (onprotection (fare behalf of the State Debt Recovery Office) e.g.enforcement) inspection of tickets and issuing ofinfringements, p rosecution of infringement noticesImplementation of t icketing and revenuepro tection responsibilities per the SLR ProjectFarebox revenueChanges to faresService PaymentsChanges in serv ice levelsEscalation Ele ctricity supplyc ostsSpecia l events( unspecified)Description Deed Far ebox revenue differs from forecastFare setting responsibilityAbatement regime designed to incentivise OpCoto deliver against a set of contractually definedobjectives Increasing service levels as directed byTr ansport for NSW within certain specifiedbound s at a per-service kilometre price and/orper vehicle operating hour priceResponsibility for setting service levelsIn creasing serv ice levels as directed byTran sport for NSW beyond certain specific boundsRisk of inflation indices impacting on indexedcosts in the Service Payment ca lculationRisk of annual increases in OpCo's costs runningabove the specified indicesRisk of:• increases in costs per unit over anagreed inde x during delivery• increases in cost per unit over an agreedind ex during operations (usage andn etwork charges)• volume of consumption (ot her thanr esulting from a change in specifiedservice levels) including volume relatedto network charges• costs relating to metering charges,Australian energy market operatorcharges and any other chargesProvision of additional services required for excep t iona l, non-recurring special events (e.g.maj or sporting events, political forums)Contract s ummary 1 Sydney Light Rail ProjectType of Risk Commercia lrevenue opportunities Special events ( pre-specified)Accreditation Rail safety accreditation Financing Financing Reference interest rate riskInterest rate margin (postfinancialclose )Foreign Exchangerisk Refinancing Losses Description Cost of running recurring special events services above a level specified in the SLR Project DeedCertain advertising and other commercial opportunities Property and other opportunities retained by Transport for NSW Cost and provision of running recurring special events services as up to a level specified in theSLR Project Deed Maintaining accreditation for operation of the IWLR until handover to OpCoObtain accreditation for the SLR Works duringdelivery phaseObtaining and maintaining accreditation for theoperations and maintenance phase of IWLRObtaining and maintaining accreditation for passenger operations and maintenance of Sydney Light RailPrivat e financing of the required financingamount for the SLR PPP Risk of reference interest rate increases;• before financial close• after financial close through to 2 yearspost completion• during the operations phase (post 2years of operations )Changed interest margins post financial close Foreign e xchange rate movements• before financial close• after financial closeLosses on debt refinancing ype of Risk Tax Description Actual tax pa yable by OpCobas e case financial modeldiffers from th eOther Commercial Issues Insurance All costs and risk associated with all insurancesrequired to design, deliver, operate and maintainCSELR and IWLRForce majeure Force majeure event prevents OpCo fromperforming its obligations under the SLR ProjectDeed fo r a continuous period exceeding 180days Change i n Law or • project-specific changeNSW Government Policy • change in disability, environmental orsafe ty laws• general changeRelief events Events outside co ntrol of OpCo where OpCo isentitled to be relieved of its obligationsCompensa t ion Events outside control of OpCo where OpCo isevents entitled to be relieved of its obligations andcom pensated for the increased costs and/or lossof revenue that it incursOverview of the Sydney Light Rail PPP 8. Participants in the Sydney Light Rail PPP Public sector parties to the contracts The public sector parties to the SLR PPP are:( a) Transport for NSW (ABN 18 804 239 602) a New South Wales Government agencyconstituted by section 3C of the Transport Administration Act 1988 (NSW); and{b) the NSW Treasurer, for an on behalf of the State of New South Wales, who hasexecuted a guarantee by the State of Transport for NSW's performance of itsobligations und er several of the project's contracts, see section 30 (Liabilities,ind emnities and guarantees given by the Crown) of this report.Private sector parties to the contracts The main private sector parties are:OpCo group (a) ALTRAC Light Rail Partnership, a partnership between:(i) AL TRAC Light Rail 1 Pty Limited ACN 603 192 203 in its capacity as trusteeof ALTRAC Light Rai l Trust 1;( ii) AL TRAC Light Rail 2 Pty Limited ACN 603 194 476 in its capacity as trusteeof A LTRAC Light Rail Trust 2; and( iii) ALTRAC Light Rail 3 Pty Limited ACN 603 190 601 in its capacity as trusteeof ALTRAC Light Rai l Trust 3.(b) All of the units in the ALTRAC Light Ra il Trust 1 are held by ALTRAC Light RailHoldings 1 Pty Ltd ACN 603 167 380.(c) A ll of the units in the ALTRAC Light Rail Trust 2 are held by ALTRAC Light RailHoldings 2 Pty Ltd ACN 603 192 221.(d) A ll of the units in the ALTRAC Light Rail Trust 3 are held by ALTRAC Light RailHoldings 3 Pty Ltd ACN 603 185 655 in its capacity as tru stee of the ALTRAC LightRa il Holdings Trust 3.OpCo group equity investors (a) Acciona Concesiones S.L or one of its wholly owned subsidiaries, with a 5%owne rship interest.(b) FSS Trustee Corporation, in its capacity as trustee of the First StateSuperannuation Scheme or one of its Associates, with a 62.5% ownership interest.(c) John Laing Investments {SLR) B.V. or one of its wholly owned subsidiaries, withan eq uity interest of 32.5%.Con tract summary 1 Sydney Light Rail Project Page 18Transport for NSW Figure 2: OpCo group structureALTRAC Light Rail Structure Core Contractors and Co re Contractor GuarantorsALlRAC l!lght Rail 3ptyUd (ACN 603:190601) (a) Alstom Transport Australia Pty Limited ABN 68 165 157 451 and AccionaInfrastructure Australia Pty Ltd ABN 52 140 915 251 (together the D&CContractor) . OpCo has subcontracted its obligations to design and construct the SLRWorks to the D&C Contractor under the D&C Contract on a joint and several basis.The D&C Contractor has also entered into an associated side contract with Transport for NSW .(b) Transdev Sydney Pty Ltd ABN 34 096 046 052 (O&M Contractor). OpCo hassubcontracted its obligations to operate and maintain the Sydney Light Rail to theO&M Contractor under the O&M Contract. The O&M Contractor has also entered intoan associated side contract with Transport for NSW.The D&C Contractor and the O&M Contractor are collectively referred to as the CoreContractors. (c ) Acciona Infraestructuras S.A. and ALSTOM Transport S.A. (each a D&CGuarantor) and Transdev Australasia Pty Ltd ABN 40 079 303 816 (O&MGuarantor). These guarantors have entered into parent company guarantees withOpCo to guarantee certa in liabilities and obligations of each Core Contractor.Independent Certifier APP Corporation Pty Ltd ABN 29 003 764 770 has been jointly engaged by Transport forNSW and OpCo to carry out independent certification services in relation to the SLR Works.Debt financing parties CBA Corporate Services {NSW) Pty Limited ACN 072 765 434 has been engaged byOpCo as the Security Trustee and Commonwealth Bank of Australia ACN 123 123 124has been engaged by OpCo as the Agent and have entered into, amongst others theSyndicated Facility Agreement, the Financiers Tripartite Deed and the Security Trust Deed.Astra SLR Finance Pty Limited ACN 166 382 403 of c/- Capella Capital, is a specialpurpose company which was established to raise debt finance for the PPP and to securitiseOpCo's licence payment obligations. The debt raised by Finance Co is contributed to OpCoby way of a securitised licence payment structure governed by the "SecuritisationAgreement", see section 9.Finance Co means Astra SLR Finance Pty Limited ACN 166 382 403.9. Contractual structure of the Sydney Light Rail PPP Introductory summaries of the contractual structure of the SLR PPP as at 17 December2014, in so far as the contracts affect or will potentially affect public sector rights andobligations, are summarised in a simpl ified form below.The principal contract is the SLR Project Deed dated 17 Dece_mber 2014 between Transportfor NSW and OpCo. This contract comprises a "Deed of Agreement" and attached to this Deed of Agreement are 79 "Schedules" (including 50 "Appendices" forming part of Schedule E1), and thecomplete contract is described in this report simply as the SLR Project Deed.The SLR Project Deed sets out the terms under which:(a) OpCo must finance, or procure finance for, the SLR PPP; ( b) OpCo must design and construct the SLR Works and operate and maintain the IWLRand the CSELR; and(c ) OpCo must hand the Sydney Light Rail back to Transport for NSW at the end of thecontract term. Financing OpCo will satisfy its obligation to finance, or p rocure finance for, the SLR PPP through :(a ) Equity investments by the project's equity investorsIn line with the NSW Public Private Partnerships Guidelines 2012 and the expressconfidentia lity provisions of the contracts, see section 10 (Confidentiality ande xcluded material), the details of the equity investors' obligations are generallybeyond the scope of this summary.(b) Loans to Finance Co and the securitisation of OpCo's licence paymentobligations Finance Co , OpCo and Transport for NSW have entered into the "ReceivablesPurchase Deed " under which Finance Co will purchase Transport for NSW's right toreceive licence payments pa yable by OpCo under the SLR Project Deed in respect ofthe permanent light rail corridor and the non-corridor assets. In consideration for theassignment of the right to receive the licence payments, Finance Co pays Transportfor NSW monthly 'receivables purchase payments'. Transport for NSW uses the' receivables purchase payments' to fund its obligation under the SLR Project Deed topay OpCo- see section 17 (Price) of this report.Finance Co will borrow the funds which it needs to pay each 'receivables purchasepayment' from a syndicate of lenders under the "Sydney Light Rail PPP -Syndicated Facility Agreement" dated 13 February 2015 (Syndicated FacilityCon tract summary 1 Sydney Light Rail Project Page 20Transport forNSW Agreement). Finance Co uses the licence payments it receives from OpCo as aresu lt of the assignment described above to service the debt it borrows under theSyndicated Facility Agreement.The " Payment Directions Deed" entered into by Transport for NSW, OpCo,Finance Co and Commonwealth Bank of Australia (as Agent) dated 13 February2015, is an ancillary document to the Receivables Purchase Deed which allows thevarious securitisation related payments to be made directly from the original partymaking the payment to the end recipient, without the need for separate interveningtransfers between the parties. In addition, there are intercompany loans in place between OpCo and Finance Copursuant to which debt raised by Finance Co can be on-lent to OpCo outside of thesecuritised licence payment structure as required.In line with the NSW Public Private Partnerships Guidelines 2012 and the expressconfidentiality provisions of the project's contracts - see section 10 (Confidentialityand excluded material) of this report - the details of the project's debt fina ncingarrangements are generally beyond the scope of this summary.Design and construct and operations and maintenance OpCo wi ll satisfy its obligations to design and construct the SLR Works and operate andmaintain t he Sydney Light Rail through:(a) The performance by the D&C Contractor of their joint and several obligations toOpCo to design and construct the SLR Works under the "Sydney Light Rail D&CContract" between OpCo and the D&C Contractor dated 17 December 2014 (D&CContract) .(b) The performance by the O&M Contractor of its obligations to OpCo to operate andmaintain the Sydney Light Rail and electronic ticket ing system equipment under the" Sydney Light Rail O&M Contract" between OpCo and the O&M Contractor dated17 December 2014 (O&M Contract).The D&C Contract and the O&M Contract are collectively referred to as the CoreContracts. (c) T he performance by each Core Contractor of their obligations to OpCo to cooperateand liaise with each other as set out under the "DCOM Interface Agreement"between OpCo and each Core Contractor dated 17 December 2014. This deedresolves key subcontract interface issues such as input into design documentationand project plans, consultation, maintenance and responsibility for approvals.(d) The performance by the Independent Certifier of its obligation to provideindependent certification of the SLR Works under the "Independent CertifierDeed" between Transport for NSW, OpCo and the Independent Certifier dated 17December 2014.(e ) The performance by the D&C Independent Certifier of its obligation to provideindependent certification of the SLR Works under the "D&C Independent CertifierDeed" between OpCo, the D&C Contractor, the D&C Independent Certifier and theSecurity Trustee dated 13 February 2015 ..Charges The following charges have been entered into to secure Transport for NSW's rights relatingto the SLR PPP:(a) The "Deed of Charge - OpCo" between Transport for NSW and OpCo dated 17December 2014 which secures all of the obligations of OpCo to Transport for NSWunder the project contracts by charges over the assets, undertakings and rights ofOpCo. (a) The "Deed of Charge - Finance Co" between Transport for NSW and Finance Codated 17 December 2014 which secures all of the obligations of Finance Co toTransport for NSW under the Receivables Purchase Deed, Payments Direction Deedand Financiers Tripartite Deed by charges over any of the assets, undertakings andrights of Finance Co.(b) The "Deed of Charge- O&M Contractor" between Transport for NSW and the O&MContractor dated 17 December 2014 which secures the O&M Contractor's return to OpCo of the Sydney Light Rail and any electronic ticketing system equipment andrequ ires the O&M Contractor to transfer all of its rights, title and interests (if any) inthe assets to OpCo free from any security interests. This charge is a specific se curityi nterest over Transport for NSW's assets, interests, rights and proceeds in respect ofwhich the O&M Contractor has right to grant a charge over. Other (a) The "Dispute Avoidance Board Agreement" between Transport for NSW, OpCoand each DAB Member dated 12 February 2015. This agreement establishes theDispute Avoidance Board (DAB) and will assist in the avoidance and effectivemanagement of disputes throughout the term of the project. It sets out the rights,obligations and duties of the each DAB Member, Transport for NSW and OpCo.(b) The "Aistom CSELRV Supply Agreement" between Transport for NSW and Alstomdated 17 December 2014. Under this agreement Transport for NSW has two optionsto purchase additional LRVs from Alstom and sets out the terms for those optionsand for the delivery of the LRVs, if exercised.(c) The "Equity Purchase Deed" was also entered into by Transport for NSW, HoldCo1, HoldCo 2, HoldCo 3, Acciona Concesiones S.L., FSS Trustee Corporation and John Laing In vestments (SLR) B.V. dated 17 December 2014. This deed confers onTransport for NSW the right to purchase the equity capital of HoldCo1, HoldCo 2 andHoldCo 3, and sets out the related terms and conditions on when this right may beexercised by Transport for NSW.(d) Some of Transport for NSW's rights and obligations under the SLR Project Deed andeach Core Contractor Side Deed are subject to restrictions or additional processrequirements under the "Financiers Tripartite Deed" between Transport for NSW,OpCo, Finance Co, the Security Trustee, the Agent and Commonwealth Bank ofAustralia dated 13 February 2015. As an example, this agreement requires Transport for NSW to notify the Security Trustee and the Agent before it terminates the SLRProject Deed for a default by OpCo, giving the Security Trustee an opportunity tocure the default . Priorities between Transport for NSW's charges and securities heldby the project's private sector debt financ iers are also governed by the FinanciersTripartite Deed .(e) The "Escrow Agreement" which sets up arrangements ensuring Transport for NSWwill be able to exercise its rights under the SLR Project Deed to obtain the sourcecode of various computer programs used and developed by OpCo and its contractorsbetween Transport for NSW, OpCo, Alstom and Assurex Escrow Pty Ltd dated 12February 2015. (f) In addition, separate "Deeds of Assurance'', entered into between Transport forNSW, OpCo and Alstom Transport Australia Pty Ltd (the Licensed IP Owner) andbetween Transport for NSW, OpCo and Alstom Transport Technologies SAS (theLicensed IP Owner). These deeds assure Transport for NSW and any entityauthorised or licensed by Transport for NSW that Transport for NSW may continueexercising its rights under the SLR Project Deed licence, notwithstanding any changeaffecting the Licensed IP Owner's direct or indirect relationship with OpCo.(g) Under the "PAFA Act Deed Poll of Guarantee" executed by the NSW Treasurer (onbehalf of the State of NSW) in favour of OpCo and the Security Trustee dated 17December 2014, the State of NSW provides a guarantee of Transport for NSW'sob ligations. See section 30 (Liabilities, indemnities and guarantees given by theCrown) for further information.The contracts listed above to which Transport for NSW is a party (amongst others) arereferred to as the Transport for NSW Project Agreements throughout this report.A diagrammatic representation of the contract structure appears below and shows themain contracts only.Figure 2 : Contract structureConfidentiality and excluded material Under their own terms all of the SLR PPP major contracts and associated documents towhich Transport for NSW is a party, including the SLR Project Deed, may be publiclydisclosed by Transport for NSW, provided in all cases Transport for NSW redacts anyc ommercially sensitive information.Each category of commercially sensitive information is summarised below.The SLR Project Deed prohibits the release, except in specified circumstances, ofinformation revealing: (a) OpCo 's debt financing and equity arrangements, including terms, fees and margins;(b) the cost structures, profit margins and intellectual property of OpCo and itssubcontractors; (c) OpCo's "base case" financial model for the SLR PPP and the financial close protocol;(d) any values or monetary va lu es, including those used to calculate the net financialimpact o r any termination payment;(e) any va lue, percentage, rates, fees, escalation factors or formulas used to calculatethe Service Payment or any other payment to OpCo;(f) the terms of the Core Contracts, each significant contract, the D&C Guarantee, theO&M Guarantee and the DCOM Interface Agreement;(g) the terms of the project contracts to which Transport for NSW is not a party;(h) the terms of the projects' insurance policies;(i) any te rms that could prejudice the legitimate business, commercial, professional orfinancial interests of a party to the project contracts; or(j) any te rms where disclosure would place a party to a project contract at a substantialcommercial disadvantage in projects of a similar nature.These confidentiality restrictions do not apply, however, to any disclosures of informationb y Transport for NSW, the State or any public authority as required under the GovernmentInf ormation (Public Access) Act 2009 (NSW) or as required to the satisfy the requirementsof the NSW Auditor General or parliamentary accountability.11. Auditor General's function The Auditor General's ability to carry out the audit functions under the Public Finance andAudit Act 1983 (NSW) have not been diminished by any of the SLR PPP contracts.Elements of the Sydney Light Rail PPP and related agreements 12. Contract term and asset transfers Term Upon execution of the SLR Project Deed on 17 December 2014, certain provisions of thecontract took effect immediately and these provisions are referred to as "Day 1 cla uses".The r emaining provisions of the contract came into effect on financial close on 25 February2015, when all conditions precedent have been satisfied (or waived). The term of the SLRProject Deed commenced on 17 December 2014 and will expire on 16 March 2034 .Transport for NSW is entitled under the SLR Project Deed to extend the term of the SLRPPP for a period of up to two years.Asset transfers All works and assets which are affixed to the Sydney Light Rail site will become and remainthe property of Transport for NSW from the time they are affixed. For example, this willinclude the stops , railway track and the maintenance and stabling facilities.OpCo must ensure that ownership of the Moveable Assets, including the LRVs, spares,specia l tools and equipment and other chattels forming part of the works (but excludingany hired assets), transfers to Transport for NSW, at no cost, on the date on which OpCoacquires title to the relevant moveable asset, free from any security interests (other thanpermitted security interests).At the end of the term OpCo must transfer, at no cost, all of OpCo's rights and interests in the assets to Transport for NSW (or its nominee) free from any security interest and in astate whic h complies with the requirements of the SLR Project Deed.See section 26 (Transfer of assets by the public sector to the contractor) of this report forfurther details regarding the transfer and use of assets by OpCo and its contractors.13. Primary obligations OpCo's primary obligations under the SLR Project Deed are to:(a) finance or arrange for the financing of the SLR PPP;(b) design and construct the SLR Works;(c) operate and maintain the Sydney Light Rail and the electronic ticketing systemduring the contract term; and(d) hand the Sydney Light Rail back to Transport for NSW at the end of the contractterm. Transport for NSW's primary obligations under the SLR Project Deed are to :(a) grant OpCo licences to use and occupy:(i) the construction site;(ii) the permanent light rail corridor; and(iii) specified assets which OpCo must maintain; and' (b) make various payments to OpCo, which are explained in more detail in section 17(Price) of this report.14. Activities of Transport for NSW and OpCo during the construction period OpCo construction works OpCo is responsible for the design and construction of the SLR Works, which comprise :(a) the CSELR, including trackwork, rail structures, rail systems, interchange facilities,terminus facilities, CSELRVs and stops;( b) LRV stabling facility at Randwick and a maintenance facility at Rozelle;(c) wo rks on the electronic ticketing system, including all works associated with theintegration of civil and cabling works, such as power supply and data communicationthat relates to the electronic ticketing equipment;(d) modification, reinstatement and improvement of local areas, including all publics paces, parks, pedestrian ways, pedal cycle paths, and roads which are in any wayaffec ted by the works undertaken by OpCo (Local Area Works);(e) works required for existing buildings and infrastructure or to property identified inthe SLR Project Deed (Property Works);( f) any modification or relocation of any service, facility or item of infrastructure for theprovision and measurement of water, electr ici ty, gas, ethane, fuel, telephone,drai nage, sewerage, industrial waste disposal and electronic communication service( Utility Service Works);(g) works at Alison Road; and(h) property noise attenuation works.During the construction phase OpCo must:(a) co nstruct t he SLR Works and the temporary works in accordance with the SLRProject Deed (including the Scope and Performance Requirements (SPR)), the finalde sign documentation and any modifications directed or approved by Transport forNSW; (b) use workmanship of the standard set out in the SPR and which is fit for purpose;(c) use materials which comply with the requirements set out in the SLR Project Deed(incl uding the SPR) and which are free from defects and are safe and fit for theirin tended purpose; and(d) meet a ll sustainability requirements specified in the SPR.OpCo wa rrants that the SLR Works will, upon complet ion and thereafter at all relevantt imes, be 'safe and fit for their intended purposes.Laws and approvals In performing its activities, OpCo must comply with all applicable laws including thoser elating to environmental heritage. Transport for NSW has obtained or will obtain theplanning approvals required for the SLR PPP. Transport for NSW bears risk of any legalc hallenge to these planning approvals.OpCo is responsible for:(a) obtain ing all other approvals;(b) obtaining licences under the Protection of the Environment Operations Act 1997 (NSW); and( c) complying with all conditions of all approvals (other than those conditions of theplanning approvals which Transport for NSW has specifica lly agreed to comply with).Sydney Light Rail site Transport for NSW has granted to OpCo a non-exclusive licence to use and occupy theconstruction site during the delivery phase and the permanent light rail corridor and noncorridorassets during the operations phase.Any archaeological or heritage artefacts discovered on or under the Sydney Light Rail si tewill, (as agreed between Transport for NSW and OpCo) be the absolute property ofTransport for NSW. OpCo must immediately notify Transport for NSW if any artefacts arediscovered, protect them and comply with any Transport for NSW instructions, includingany directions to suspend work.Section access Transport for NSW and OpCo have agreed a section access regime that incentivises OpCoto minimise disruption during construction. OpCo will be liable for a daily fee for each daythat its occupation of a zone exceeds an agreed base occupation period. Where OpCovacates a zone earlier, it will be entitled to a cred it. OpCo's liability for daily fees andentit lement to credits are capped .Time OpCo is obliged to use its best endeavours to achieve completion of the SLR Works by the'original date for completion', being 16 March 2019. OpCo does not receive any payment(other than in respect of the IWLR) until completion is achieved .If OpCo is delayed in achieving completion by a 'relief event' - see section 18 (Reliefevent s) of this report- OpCo may make a claim for an extension of time. If granted and therelevant 'relief event' was also a 'compensation event', OpCo may claim for compensationin respect of the net financial impact of the period of time for which the extension of time was granted.Transport for NSW may, in lieu of granting an extension of time, elect to compensate OpCofor the additional negative net financial impact incurred by OpCo arising from not grantingOpCo an extension of time.If OpCo fails to achieve completion within 2 yea rs after the 'date for completion', Transportfor NSW will be entitled to terminate the SLR Project Deed - see section 22 (Terminationrights) of this report.Ultimately, OpCo retains the risk of design and construction of the SLR Works not beingcompleted on time or to budget for reasons other than a risk borne by Transport for NSW.If OpCo becomes aware of a matter which will, or is likely to delay completion, it mustnotify Transport for NSW and prepare a correcti ve action plan in respect of the delay. OpComust take reasonable steps to avoid or minimise the effects of any delay.OpCo must update the delivery program regularly to reflect changes to the program,delays, corrective action plans and any other details required by Transport for NSW.15. Service delivery and quality requirements OpCo is required to operate the Sydney Light Rail for the contract term, including theoperation and maintenance of LRVs, stops and the light rail maintenance and stablingfacilit ies so that the Sydney Light Rail remains fit for its purpose at all times during thecontract term. OpCo must operate the Sydney Light Rail to provide se rvices in accordance with thecontract serv ice level requ irements and provide the minimum required services, includingadditional services for special events.Operations review Either party , at any time, may request that the other party participates in a review of theoperations activities, including to consider factors such as measures to improve andaddress the reliability of services, patronage demand, modal coordination and seasonalityissues, measures to address material changes to intersection wait times, trends andchanges in the demographics , land use and infrastructure that may impact the services,measures to overcome any identified inefficiencies, recommendations ansmg fromincidents and accidents, measures to address security issues or matters that affectcustomer safety and security, changes to minimum operating standards, contract servicelevel requirements or staffing levels or any other factors that Transport for NSW or OpCoconsiders relevant. Transport for NSW may request changes to the contract service level requirements (withinspecified levels) and either party may otherwise request a modification to the servicelevels. Transport for NSW wi ll be required to direct a modification to services in certaincircumstances including where patronage e xceeds certain levels or where there is a changein traffic light priority or speed limits.Operational respons ibilitiesOpCo 's operational responsibilities include:(a) provision of information: providing real-time information to Transport for NSWand customers, ensuring that current, accurate, up to date and relevant information relating to the services and the Sydney Light Rail is provided to customers andcooperating and sharing information with other public transport providers ;(b) ticketing, fare collection and revenue protection: providing customers withticketing and fare information, protection of fare revenue, issuing penalty notices forfare evasion and reporting any faults with the electronic ticketing system;(c) security: operating and maintaining a CCTV system and CCTV surveillance; and(d) cleaning and presentation: monitoring and ensuring that the light rail vehicles,stops, electronic ticketing system and assets are clean and graffiti is removed andvandalism rectified in accordance with the SLR Project Deed.Service Payment OpCo's monthly Service Payment will be reduced to the extent that OpCo fails to meet thecontract service le vel requirements. See section 17 (Price) of this report for furtherinformation regarding the calculation of the Service Payment.16. Maintenance OpCo must maintain the specified assets so that the Sydney Light Rail remains fit forpurpose during the contract term and each asset (provided it is operated and maintainedafter the end of the contract term in accordance with the asset management system) iscapable of remaining fit for its intended purpose throughout the design life of that asset, or in the case of a replacement or refurbished asset, the extended design life of that asset.OpCo must also rectify all defects (fair wear and tear excepted) within a reasonable time,subject to specified exceptions within the SLR Project Deed. Asset management plan and asset information system OpCo must maintain the minimum specified stock of spares for the assets and prepare and update the asset management plan . The asset management plan must cover all specifiedassets and include a ma intenance works program which describes the asset managementactivities for the following two year period. OpCo must also provide and maintain an asset information system that:(a) covers all assets;(b) records OpCo's compliance with the asset management plan, including the conditionof, and changes to condition of, assets and the remaining life of the assets;(c) is capable of producing period reports that allow OpCo and Transport for NSW tomonitor asset conditions and compliance; and(d) at all times accurately represent the true status and condition of all assets and assetmanagement activities. Transport for NSW is the owner of all information held within the asset information systemand may access it at any time in accordance with the SPR.The parties will meet annually within 3 months of the end of each operating year until theend of the contract term to review OpCo's compliance with the maintenance work program.Asset management failure An "asset management failu re" will occur if OpCo fails to comply with the maintenanceworks program and this failure constitutes a material non-compliance with the assetmanagement plan. Where OpCo fails to remedy such failure within the required period,Transport for NSW may withhold a specified amount from the Service Payment each monthuntil the failure is remedied. Reporting OpCo must provide to Transport for NSW's representative monthly, quarterly and annualreports on the asset management activities during the operation of the Sydney Light Rail.Handback audit and f inal inspectionPrior to the original expiry date of the SLR Project Deed (no earlier than 18 months and nolater than 6 months), Transport for NSW's representative may procure an audit of theSydney Light Rail. An independent expert will inspect and assess the assets specified forhandback and identify any rectification, maintenance or remediation works required. OpComust carry out such works to the satisfaction of the independent expert and so as tosatisfy the standards and requirements under the SLR Project Deed.As soon as practicable following the end of the contract term, an independent expert willinspect and assess the Sydney Light Rail and notify Transport for NSW and OpCo of theestimated cost of making good or rectifying any failure by OpCo. The amount notified bythe expert will be a debt due from OpCo to Transport for NSW and Transport for NSW maydeduct or set off this amount against any other amount otherwise payable to OpCo.If the term is extended beyond the original expiry date of 16 March 2034, OpCo mustensure at this date that the specified assets are in the required state and condition and aninterim inspection of the assets will be carried out.17. Price Payment obligations Transport for NSW must make the following payments to OpCo or, in the case of the CDPDAmount , pay Finance Co:(a) monthly operations and maintenance payment during the IWLR operations phase;(b) monthly Service Payments during the full operations phase upon completion of theCSELR; Co nt ract summary 1 Sydney Light Rail Project Page 29Transport for NSW (c ) if certain conditions have been met between year 2 and year 4 of the full operationsphase, a lump sum 'conditional debt pay down' amount equal to the lesser of 50% ofdebt forecast o utstanding and 50% of debt actually outstanding, on the paymentdate; (d) any bo nus payments for early completion, if applicable; and(e) a ny pre-agreed option payments, if exercised.It is est imated that the net present value of the Service Payments for the SLR PPP over19.1 years is $2,200.4 million.Service Payment mechanism Monthly Service Payments will be made to OpCo once services have commenced . TheService Payments will cover OpCo's cost of financing , design, construction, assetmanagement and performance of operations on the entire Sydney Light Rai l network.The Service Payment will be determined in accordance with the payment mechanism thatis designed to incentivise OpCo to deliver the requirements of the SLR Project Deed(inc luding the SPR) and includes: •(a) a service-based payment with no demand risk, with Transport for NSW retainingr evenue and the responsibility for setting fares;(b) a deduction regime which will reduce OpCo's Service Payment if it fai ls to meettime liness, availability and revenue management requirements and key performanceindicators (KPis) based on the SLR PPP's output specification;( c) an appropriate "bedding in" period for the abatement regime to enable OpCo toestablish its operational performance; and ( d) incentive payments for customer satisfaction and revenue management to encourageand reward OpCo for e xceptional performance.Service Payment calculation The Se rvice Payment each month is comprised of:(a) an indexed availability fee; plus(b) t he benchmarked insurance component; plus(c) an indexed lifecycle component; minus(d ) an availability deduction (measured against missed services); minus(e) a timeliness deduction (measured against frequency of services and total journeytime) ; minus(f) a service quality deduction (measured against the service quality KPis describedbelow ) ; minus(g) a revenue management deduc~ion (measured against the service quality KPisdesc ribed below); plus(h) the energy amount bid (measured against the base energy volume and base networkvo lume); minusCo nt ract summary 1 Sydney Light Rail Project Page 30Transport for NSW (i ) an energy adjustment (measured against a demand usage strategy designed tominimise network demand charges); plus(j) a customer satisfaction payment (measured against customer satisfaction surveys);p lus(k) a revenue management payment; plus( I) an asset management adjustment (measured against compliance with themaintenance works program); plus(m) the floating rate amount (measured against quarterly interest rate movements) 2years post the Date for Completion; minus(n) the final completion deduction amount (calculated in months where OpCo has notachieved final completion); minus( o) Transport for NSW's share of gross commercial revenue; minus(p) the ticket co llection amount; and minus(q) the traffic signal aggregate delay amount (measured against the traffic signal delayset out in the SPR).The SLR Project Deed also sets out a regime that allows Transport for NSW to request'service level adjustments', being short and long-term adjustments to the services, whichwill subsequent ly impact the calculation of the Service Payment.Key Performance IndicatorsOpCo's performance will be assessed and measured each quarter during the operationsphase against the service quality KPis set out below.If OpCo fails to meet the required quality standards OpCo's Service Payment will bereduced and calculated based on the respective KPI scores and weighting up to ama ximum deduction amount.Cont ract summary 1 Sydney Light Rail Project Page 31Transport forNSW Table 4: Key performance ind icatorsKPI Service Quality KPisno 1 Vehicle cleanliness, condition and graffiti2 Stop and interchange cleanliness, condition and graffiti3 Corridor cleanliness, condition and graffiti4 Customer information5 Complaints management6 Customer satisfaction survey7 Asset availability: systems at stops8 Asset availability: systems on LRVsTotal 18. Relief Events KPI weighting 20% 10% 4 %10 %4 %3 6%6 %10 %100°/o Transport for NSW recognises that there may be events out of OpCo's control whichprevent OpCo from performing its obligations. Accordingly, the SLR Project Deedcategorises each of the following as a 'relief event':( a) a compensation event - see section 19 (Compensation Events) of this report;( b) fire, explosion, flood, storm, lightning, hurricane, mudslide, landslide, earthquakeand drought where such event of drought is declared as a state of emergency by anyperson having the requisite authority to do so and in each case occurring withinAustralia or an Alstom manufacturing country ;(c) a terrorist act within Australia;( d) war, armed conflict, riot, civil commotion occurring within Australia;( e) ionising radiations or contamination by radioactivity from any nuclear fuel or fromany nuclear waste from the combustion of nuclear fuel in each case occurring withinAustralia ;(f ) failure by any authority, or a provider of gas, water, sewerage, electricity ortelecommun ications utilities within Australia, to carry out works or provide servicesto the SLR Site which it is obliged by law (including by contract) to carry out orpr ovide, or any interruption permitted by law (including by contract) to the carryingo ut or provision of those works or services within Australia, except where the failureis a breach of a third party agreement or a utility provider agreement;(g ) any event which causes loss or damage to the Sydney Light Rail;Contract summary 1 Sydney Light Rail Project Page 32Transport for NSW (h) any b lockade or embargo in each case occurring within Australia or an Alstommanufacturing country, other than a blockade or embargo which only affects OpCoand/or o ne or more OpCo contractors;( i) any industrial action within Austra lia, other than industrial action which only affectsOpCo and/or one or more OpCo contractors;(j) a ny event or occurrence which deprives OpCo of any access t o the SLR Site that it isentitled to under the SLR Project Deed;(k) an act or omission by Transport for NSW not being an act or omission:(i) expressly permitted o r allowed by the Proj ect Agreements;(ii) which is within a timeframe expressly permitted or allowed by the ProjectAgreements; or (iii) being the exercise by Transport for NSW of any of its statutory functions orpowers; (I) an even t for which OpCo has been relieved pursuant to clause 18 of Schedule D1(Service Payment Regime) of the SLR Project Deed;(m) in respect of the Operati ons Activities during the IWLR Operations Phase and duringthe Full Operations Phase, OpCo, acting reasonably and in a manner that would beexpected of an experienced, efficient and competent operator, suspends or cancels aService to avoid or protect against a rea l or apparent public danger caused by anI ncident; and(n) certain specified relief events relating to Alstom and which affects an additionalCSELRV or an option CSELRV,except to the extent the event (or its effects):(o) occurs or arises as a direct or indirect result of any act or omission of OpCo orOpCo's Cont ractors;( p) occurs or arises as a direct or indirect result of a failure by OpCo to comply with itso bli gations under the SLR Project Deed;( q) occurs or arises as a direct or indirect result of any breach of the SLR Project Deedby OpCo; or (r) is, or ought reasonably to have been , within the control of OpCo or OpCo'sContractors. If a 'relief event' occurs, OpCo must notify Transport for NSW within 10 business days thata relief event has occurred. Within 10 business days of giving this notice, OpCo must giveTransport for NSW full particulars of the relief event including (to the extent practicable)details of the obligations which have been affected, steps taken to mitigate, and whetherOpCo conside rs the event may also give rise to a 'force majeure event', see below.If OpCo satisfies various notice requirements, OpCo will not be in breach of any of itsobligat ions which are affected by the 'relief event' (other than payment obligations), buton ly to the extent the 'relief event ' prevents OpCo from performing those obligations. OpComus t use all reasonable endeavours to mitigate the effects and, in contrast to'c ompensation events', and despite the occurrence of a 'relief event', the ca lcu lation of theCont ract summary 1 Sydney Light Rail Project Page 33Transport for NSW Service Payment during the affected period will occur as if OpCo's obligations arecontinuing and the Service Payment may be deducted accordingly.Force majeure events If a 'relief event' (other than a 'compensation event' or a 'relief event' described inparagraphs (b) and (h) above to the extent occurring in an Alstom ManufacturingCountry): (a) exists or occurs, or the impacts of which exist or occur for a continuous periodexceeding 180 days; and(b) directly causes OpCo to be unable to achieve completion or to comply with a materialpart of its obligations under the SLR Project Deed,then it becomes a 'force majeure event'. If a 'force majeure event' occurs, the parties must consult with each other in good faith toagree on appropriate measures to mitigate the effects and facilitate the continued performance of the SLR Project Deed. If the parties are unable to reach agreement on suchmeasures, either party may terminate the SLR Project Deed and Transport for NSW maypay a termination payment to OpCo.Transport for NSW can, within 20 business days of receipt of OpCo's termination notice,suspend OpCo's right to terminate for a maximum period of 12 months. If Transport forNSW chooses to suspend OpCo's right to terminate, Transport for NSW will be liable to payOpCo certain payments during the period of suspension.19. Compensation EventsThe SLR Project Deed also requires Transport for NSW to compensate OpCo for the netfinancial impact of certain events. The events that trigger this right to compensation arecalled 'compensation events' and are each of the following :(a) a breach by Transport for NSW of its obligations under the SLR Project Deed or anyother Project Agreement;(b) a legal challenge brought about by way of commencement of court proceedings inrelation to a planning approval except to the extent the legal challenge was due to amodification requested by OpCo or a failure by OpCo to comply with its obligationsunder the SLR Project Deed;(c) a planning approval is modified, withdrawn, revoked or replaced except to the extentthe modification, withdrawal, revocation or replacement was due to a modificationrequested by OpCo or a fa ilure by OpCo to comply with its obligations under the SLRProject Deed ;(d) the SLR Works, the temporary works, the Sydney Light Rail site or the Sydney LightRail are damaged by another contractor engaged by Transport for NSW;( e) OpCo, or an OpCo Contractor, is required to comply with an environmental notice orrequired by any law, approval, environmental notice or otherwise to dispose of,otherwise deal with or remediate contamination, which in each case does not ariseout of or in connection with any contamination for which OpCo is responsible;(f) Transport for NSW fails to give OpCo access to the construction site in accordancewith the SLR Project Deed;Con tract summary I Sydney Light Rail Project Page 34Transport for NSW (g) if OpCo is directed, ordered or required to cease to perform OpCo's Activities (or tochange the way it does so), or to provide reasonable assistance in connection withdealing with a native title claim;(h) the occurrence of a compensable change in law;(i) the occurrence of a compensa ble change in NSW government policy;(j) a step-in party exercises all or any of the step-in powers in respect of a step- inevent; (k) if the SLR Works, the temporary works, the Sydney Light Rail, the Sydney Light Railsite or OpCo 's activities are damaged or adversely affected by any proximate workactivity; ( I) before the date of completion the occurrence of a 'utility works event';(m) an·y 'existing asset defect' occurs and such occurrence has, or is likely to have, amateria l impact on required services;( n) the discovery of hazardous coal tar pursuant to the SLR Project Deed; and(o ) Transport for NSW cancels a connection shutdown pursuant to the SLR Project Deedand OpCo, using its best endeavours, is not able to reschedule the connectionshutdown so it is not on the critical path,e xcept to the extent the event (or its effects):(p) occurs or arises as a direct or indirect result of any act or omission of OpCo orOpC o's Contractors;(q) occurs or arises as a direct or indirect result of a failure by OpCo to comply with itsobligations under the SLR Project Deed;(r) occ urs or arises as a direct or indirect result of any breach of the SLR Project Deedb y OpCo; or(s) is, or ought reasonably to have been, within the control of OpCo or OpCo'sContractors. To the extent that OpCo incurs additional costs or loss of revenue and provided it compliesw ith certain condition precedents, OpCo will receive compensation from Transport for NSWfor the net f inancial impact of the 'compensation event'. OpCo will also receive relief frombeing in breach of its obligations to the extent that OpCo's non-performance is caused bythe 'compensation event' and may receive an extension of time to the 'date forcom pletion', see section 14 (Activities of Transport for NSW and OpCo during theconstruction period) of t his report.OpCo must take all reasonable steps to mitigate the effects of any 'compensation event'and use its best endeavours to continue to perform its obligations despite the'co mpensation event'.Co ntract summary I Sydney Light Rail Project Page 3520 .Transport for NSW Modifications and augmentations Transport for NSW initiated modificat ionsTransport for NSW may modify the SLR Project Deed requirements relating to the SydneyLight Rail or OpCo's activities. The SLR Project Deed gives Transport for NSW the right torequire OpCo to carry out the following categories of modifications:(a) Emergency modification: any modification which Transport for NSW believes,acting reasonably is requi red to prevent, mitigate or repair any threat, or likelythreat, to the safety of any customer or other person, prevent, mitigate or repair anyca use, or likely cause, of significant damage to the Sydney Light Rail, prevent,mitigate or repair any suspension, interruption, or likely suspension or interruption,to the operation of the Sydney Light Rai l, or to discharge a legislative or public duty;( b) O&M Modification : a modification that requires OpCo to operate and maintain anye xtension to the Sydney Light Rai l designed and constructed by Transport for NSW,its associates or other contractors;(c) Operations Modification: a modification that requires OpCo to operate over, butnot maintain, any extension to the Sydney Light Rail designed, constructed andmaintained by Transport for NSW, its associates or other contractors;(d) Expansion Modification: a modification that extends the Sydney Light Ra il by nol onger than 20% of its length (such length to include parts of the Sydney Light Railwh ich are under construction or already contracted to be constructed whether or notcons truction has commenced) and requires OpCo to design, build, operate andmaintain the extension contemplated; and(e) LRV O&M Modification : a modification that requires OpCo to operate and maintainadditional light rail vehicles for the Sydney Light Rail purchased by Tra nsport forNSW f rom a third party.Transpo rt for NSW will compensate OpCo for the net financial impact of t he modificationand grant any relief necessary.OpCo initiated modifications OpCo may propose a modification to the SLR Project Deed. Transport for NSW has absolutedi scretion to approve or reject the proposed modification.OpCo bears all ri sks and costs associated with a modification proposed by OpCo (unlessot herwise agreed by Transport for NSW).Pre-agreed options Tra nsport for NSW and OpCo have negotiated the following pre-agreed options that havethe potent ial to expand or reduce the scope of works for the SLR PPP:(a ) Additional CSELRVs: Transport for NSW has the right to the following options topurc hase additional CSELRVs :( i) Option la: supply of two additional CSELRVs and any other associated capitalcosts (which may include stabling changes) as a follow-on order to the initialpurchase to be exercised no later than 31 December 2016. Delivery of theseadditional CSELRVs will be required by the date of completion but will notform part of the completion requirements;Contract summary 1 Sydney Light Rail Project Page 36Transport for NSW (ii) Option lb: supply of 4to 16 additional CSELRVs and any other associatedcapital costs (which may include stabling changes) to be exercised from 1January 2017 to 1 March 2019; and (iii) Option 2: supply of 4to 16 additional CSELRVs and any other associatedcapital costs (which may include stabling changes) to be exercised from 1March 2019 to 1 March 2024.The CSELRV options work on an aggregate basis for Options 1b and 2 so that nomore than 16 additional CSELRVs in total can be ordered.(b) IWLRV option : if Transport for NSW elects to exercise the option for up to 12additiona l IWLRVs to be operated and maintained by OpCo to provide services, theparties have agreed to cooperate with each other and act in good faith in relation tothe implementation of such modification.(c) Anzac Parade option : Transport for NSW has the right to exercise one of eithertwo options in relation to traffic diversion on Anzac Parade, being:(i) five lanes on Anzac Parade with temporary lane shifting on the eastern side ofAnzac Parade only; or(ii) five lanes on Anzac Parade with temporary lane shifting on both sides ofAnzac Parade. Either option will entitle Transport for NSW to a price reduction and the last date onwhich Transport for NSW may exercise either option is 30 August 2015.Augm entationsThe SLR Project Deed establishes a framework by which an augmentation can be d iscussedand potentially agreed upon by the parties. It is distinct f rom a modification, which aregenerally variations within the scope of works contemplated by the parties.Tran sport for NSW may at any time propose an augmentation to OpCo. If Transport forNSW proposes an augmentation to OpCo and does not proceed (which it may do so at itsdiscretion at any time) , OpCo will be entitled to costs reasonably and properly incu rred asagreed b y the parties in accordance with the principles set out in the SLR Project Deed .Transport for NSW has the right to terminate the SLR Project Deed or exercise the equitypurchase option in circumstances where an augmentation is not agreed between theparties. 21. Defaults under the SLR Project Deed OpCo Events of Default Each of the following will be an 'OpCo event of default':( a) failure to commence revenue service: OpCo fa ils to commence revenue serviceon the IWLR by 1 July 2015 or such later date as the parties have agreed;(b) failure to progress: OpCo fails to diligently progress the delivery activities asrequi red ;(c) funding cancelled: the obligation of a debt financier or an equity investor toprovide funding under the debt financing documents or the equity documents,respectively, is cancelled due to an event of default under a debt financing documentor an equity document (as applicable), or a debt fina ncier or equity investor fai ls (inContract summary I Sydney Light Rail Project Page 37Transport for NSW whole or in part) to provide funding under the debt financing documents or theequity documents and no other debt financier or equity investor has committed tofunding an equivalent amount within 10 business days;(d) unacceptable availability: availability of required services falls below a specificlevel; (e) unacceptable timeliness: timeliness of required services falls below a specificlevel; (f) unacceptable quality: service quality falls below specified levels;(g ) failure to pay: OpCo fails to pay an amount that is due under any Transport forNSW Project Agreement or any Core Contract when it is due and the failure is notremedied within 10 business days (or, in the case of payment under a Core Contract,30 business days) of a written demand from Transport for NSW;(h ) failure to remedy an asset management failure: OpCo fails to remedy an assetmanagement failure within 6 months of the expiry of the remediation period;(i) failure to report: OpCo fails to comply with its reporting obligations or a reportfrom OpCo contains an inaccuracy which in either case has a material impact onTransport for NSW or customers;(j) refinancing: OpCo breaches its obligations in relation to refinancing;(k ) subcontracting : OpCo breaches its obligations in relation to subcontracting;(I) lack of or breach of accreditation : OpCo or an OpCo Contractor fails to holdrequired accreditation or breaches the terms of its accreditation;(m) threatened suspension or revocation of OpCo's accreditation : ONRSRproposes to suspend or revoke OpCo's or a Core Contractor 's accreditation, notifiesOpCo that OpCo must improve its OpCo's activities, or OpCo fails to take actionspecified by ONRSR within a time period specified by ONRSR and a failure to do sow ithin the time period specified may result in ONRSR suspending or revoking OpCo'saccreditation; (n) fraud: Transport for NSW is the victim of any fraud or dishonest conduct by OpCo ora Core Contractor in connection with the SLR PPP, or the Independent CommissionAgainst Corruption or similar public body determines that OpCo (or a CoreContractor, in performing OpCo's activities) has engaged in corrupt conduct, collusivepricing or other similar activity;(o) incorrect representation or warranty: a representation or warranty made orgiven by OpCo in the SLR Project Deed or any other Transport for NSW ProjectAgreement proves to be untrue which has a material adverse effect on OpCo's abilityto comply with its obligations; ( p) other breach : any other material breach by OpCo of an obligation (other than abreach which results in a Service Payment deduction) or any other Transport forNSW Project Agreement;( q) restriction on change in control of O&M Contractor: OpCo breaches itsobligations in relation to change in control of the O&M Contractor; andCont ract summary 1 Sydney Light Rail Project Page 38Transport for NSW (r) illegality event: any debt financing document or equity document is revoked,repudiated, terminated or ceases to be legal, valid and binding and enforceableagainst OpCo or any other person (other than Transport for NSW or the State) orany other party to a debt financing document or equity document, other than ascontemplated by the debt financing documents and equity documents or becomesin valid, void or voidable in any material respect other than where Transport for NSWhas caused it to be invalid , void or voidable or it becomes unlawful for OpCo or acore contractor to perform any of its material obligations under any debt financingdocument or equity document.If an 'OpCo event of default' occurs, Transport for NSW may issue a formal default notice.At the same time, Transport for NSW must also provide a copy of this notice toCommonwealth Bank of Australia (as the Security Trustee/Agent) under the FinanciersTripartite Deed. If the 'OpCo event of default' can be remedied, OpCo must either remedy the event within10 business days of Transport for NSW's notice or prepare and submit a draft cure plan toTransport for NSW by the same deadline, describing what OpCo will do to remedy theevent and proposing a cure period (which must not exceed 6 months). If Transport forNSW accepts an OpCo cure plan, OpCo must implement the cure plan within the cureperiod or diligently pursue the remediation of the 'OpCo event of default' in other ways.Provided OpCo is diligently pursuing a remedy, OpCo may request an extension to the cureperiod and Transport for NSW may not unreasonably refuse OpCo's first application forsuch an extension, except where the extension will result in the cure period exceeding 6months. If an 'OpCo event of default' cannot be remedied, OpCo must submit a draft preventionplan to Transport for NSW describing what OpCo will do to prevent any recurrence of theevent. If an OpCo prevention plan has been approved by Transport for NSW, OpCo mustimplement it.If OpCo fails to comply with any of its obligations following a Transport for NSW notificationof an 'OpCo event of default', as summarised above, this will constitute an 'OpCotermination event' - see section 22 (Termination rights) of this report.Persistent breaches (a) Transport for NSW may issue a persistent breach notice if OpCo breaches the sameobligation under the SLR Proj ect Deed or any other Transport for NSW ProjectAgreement more than once in any 12 month period.( b) If the relevant breach continues beyond 30 business days or recurs within the 12month period commencing 30 business days after the notice was issued, Transportfor NSW may issue a final persistent breach notice.(c) If the relevant breach continues beyond 30 business days after the issue of a finalpersistent breach notice, or recurs three or more times within the 6 month periodafter the final notice was issued, this will constitute an 'OpCo termination event' -see section 22 (Termination rights) of this report.Frequent breaches (a) Transport for NSW may issue a frequent breaches notice if OpCo commits frequentbreaches (which may be of different obligations) which, in aggregate, substantiallyfrustrate the objects of the SLR Project Deed, significantly impair Transport forNSW's ability to fulfil its statutory objectives under the Transport Administration Act1988 (NSW), have a material adverse effect on the Sydney Light Rail, the electronicticketing system or customers or in Transport for NSW's reasonable opinion indicatethat OpCo does not intend to be bound by the SLR Project Deed .Con tract summary I Sydney Light Rail Project Page 39Transport for NSW (b) If frequent breaches continue to occur during the 12-month period commencing 30business days after the notice was issued, Transport for NSW may issue a finalfrequent breaches notice. (c) If frequent breaches continue to occur at any time in the 6 month period after theissue of a final frequent breaches notice, this will constitute an 'OpCo terminationevent', see section 22 (Termination rights) of this report.Notwithstanding Transport for NSW exercising its rights in respect of a call-in, (whereTransport for NSW may notify OpCo during the operations phase that it is not satisfied), anevent of default, a persistent breach or frequent breaches, Transport for NSW may stillenforce any other rights or remedies it has in respect of such events, including its step-inrights, security rights, termination rights and its right to sue for damages.22. Termination rights Transport for NSW termination rights The SLR Project Deed entitles Transport for NSW to terminate the SLR Project Deed for anumber of reasons. The following is a summary of Transport for NSW's rights to terminate.OpCo termination events Each of the following is an "OpCo termination event":(a) failure to commence revenue service: OpCo has not commenced revenue serviceon the IWLR by 31 December 2015 or the date that is six months after such otherdate as the parties have agreed;(b) unacceptable availability: availability of required services falls below a specificlevel ;(c) unacceptable timeliness: timeliness of required services falls below a specificlevel; (d ) unacceptable quality: service quality falls below specified levels;(e) persistent breach: Transport for NSW has issued a final persistent breach noticeand the relevant breach has continued beyond 30 business days or recurred 3 ormore times within the 6 month period after the date of service of the notice;(f) frequent breaches : Transport for NSW has issued a final frequent breaches noticeand frequent breaches continue to occur at any time in the 6 month period after thedate of service of the notice;(g) failure to remedy : a failure by OpCo to remedy an 'OpCo event of default' which iscapable of being remedied within the applicable cure period;(h) failure to prevent: a failure by OpCo to prevent the recurrence of an "OpCo eventof default" which is the subject of an approved prevention plan;( i) failure to submit, amend or implement cure/prevention plan : OpCo fails tosubmit, amend or implement a cure or prevention plan;(j) failure to achieve completion by longstop date: completion has not occurred bythe longstop date; Co ntract summary I Sydney Light Rai l Project Page 40Transport for NSW (k) abandonment: OpCo abandons the SLR PPP;( I) insolvency of an OpCo partner: insolvency (of specified types) in relation to anOpCo partner; (m) suspension or revocation of accreditation : ONRSR suspends or revokes anyaccreditation required by OpCo or a Core Contractor;(n) Equity Purchase Deed: any seller is in material breach of its obligations under theEquity Purchase Deed; (o) insolvency of contractor or guarantor: insolvency (of specified types) in relationto a Core Contractor or a Core Contractor guarantor;(p) . failure to insure: OpCo does not effect and maintain (or cause to be effected andmaintained) an insurance as required by the SLR Project Deed;(q) assignment etc: OpCo breaches its obligations in relation to assignment, novationand dealing of the SLR Project Deed;(r) restriction on change of ownership of OpCo: OpCo breaches its obligations inrelation to change of ownership of OpCo;(s) restriction on change in control of D&.C Contractor: OpCo breaches itsobligations in relation to a change in control of the D&C Contractor;(t) restrictions on replacement of a significant contractor: OpCo breaches itsobligations in relation to significant contractors;(u) illegality event: the occurrence of any of the following events :(i) OpCo or a Core Contractor ceases to hold an approval or breaches a law, andsuch fai lure or breach is, in the reasonable opinion of Transport for NSW,material to the perfo rmance of OpCo's obligations under the SLR Project Deedand is not r emedied within 30 days of the earlier of the date on whichTran sport for NSW notifies OpCo of the failure or breach and the date onwhich OpCo becomes aware of the failure or breach;( ii) any project agreement (excluding the debt financing documents, equitydocuments, the Alstom CSELRV Supply Agreement and the Alstom CSELRVSupply Agreement Guarantee):(A) being revoked, repudiated or terminated or ceasing to be lega l, validand binding and enforceable against OpCo or any other person (otherthan Transport for NSW or the state) or any other party to a projectagreement (excluding the debt financing documents and equitydocuments) , other than as contemplated by the project agreements( excluding the debt financing documents and equity documents); or( B) becoming inva lid, void or voidable in any material respect other thanw here Transport for NSW has caused it to be invalid, void or voidable,and, where the event is capable of being remedied, the event is not remediedw ithin 30 days of the relevant event occurring; orContract summary I Sydney Light Rai l Project Page 41Transport for NSW (iii) it is or becomes unlawful for OpCo or a Core Contractor to perform any of itsobligations under the Project Agreements, and such event is not Remediedwithin 30 days of the relevant event occurring; and(v) failure to achieve additional CSELRV acceptance requirements by longstopdate: satisfaction of the additional acceptance requirements for CSELRVs, ascertified by the independent certifier, has not occurred by the longstop date.If OpCo becomes aware of an 'OpCo termination event', it must immediately notifyTransport for NSW. Transport for NSW may then terminate the SLR Project Deed for an'OpCo termination event' by giving a written notice that will have immediate effect.Before Transport for NSW can issue this notice however, Transport for NSW must notify theCommonwealth Bank of Australia (as the Security Trustee/ Agent), who can then ex ercisei ts rights under the Financiers Tripartite Deed to remedy the breach and discharge OpCo'sor Finance Co's obligations to the same extent as if it had been done by OpCo or FinanceCo .Termination payments - OpCo termina tion eventsIf the SLR Project Deed is terminated by Transport for NSW as a result of an 'OpCotermination event', Transport for NSW will pay OpCo:(a) the highest capital sum offered by a compliant tenderer (if the project has beenretendered) or the estimated fair value of the project (if an independent expert hasdetermined that value) and amounts due and payable by Transport for NSW toOpCo, ~: (b ) the adjusted post termination service payments paid by Transport for NSW (if anindependent e xpert has determined the estimated fair value), tender costs, amountsthat Transport for NSW is entitled to set off or deduct, amounts owed by OpCo toTransport for NSW , any gains which have or will accrue to OpCo as a result of thetermination , insurance proceeds, amounts held in certain bank accounts, amountspaid to OpCo by Transport for NSW for maintenance, refurbishment or capitalreplacement which has not been carried out by OpCo and the securitisation refundpayment. If the SLR Project Deed is terminated as a result of OpCo's abandonment of the SLR PPP,OpCo will not receive any termination payment.Transport for NSW term ination eventsEach of the following is a 'Transport for NSW termination event':(a ) any failure by Transport for NSW to comply with its payment obligations under theSLR Project Deed or the Receivables Purchase Deed that is not remedied byTransport for NSW within 20 business days of a written demand from OpCo;(b) the State e x propriates, sequesters or requisitions a material part of the Sydney LightRail or an equity interest; and(c ) a breach by Transport for NSW of the SLR Project Deed which substantially frustratesor renders it impossible for OpCo to achieve completion or comply with a materialpart of its obligations for a continuous period of two months.If a 'Transport for NSW termination event' occurs, OpCo may give Transport for NSW 30business days' notice that it intends to terminate the SLR Project Deed . Transport for NSWCont ract summary I Sydney Light Rail Project Page 42Transport for NSW may, in response, suspend OpCo's right to terminate by giving OpCo a notice to this effectwithin 30 business days of receiving OpCo's notice. If Transport for NSW takes this action:(a) OpCo must continue to perform its obligations under the SLR Project Deed during thesuspension period, to the extent it is lawful and practicable to do so; and(b) Transport for NSW must, throughout the suspension period, make monthly paymentsto OpCo t hat will place OpCo in the same net after tax position it would have been inif the 'Transport for NSW termination event' had not occurred.The suspension of OpCo's right to terminate the SLR Project Deed will continue until:(a) Transport for NSW notifies OpCo in writing that it is ending the suspension period;(b) in the case of a failure to pay, 30 business days after OpCo's termination notice;(c) in any other case, 24 months after OpCo's termination notice; or( d) when the relevant 'Transport for NSW termination event' has been remedied or itseffects overcome. If a suspension ends for any reason other than the remedying of the 'Transport for NSWtermination event', or if Transport for NSW never imposes a suspension period, OpCo mayimmediately termi nate the SLR Project Deed by giving Transport for NSW a written noticeto this effect.Voluntary termination Transport for NSW may terminate the SLR Project Deed at any time for its soleconvenience by written notice to OpCo with effect from the date stated in the notice.Termination for augmentationsTransport for NSW may terminate the SLR Project Deed if OpCo fails to remedy a materialbreach re lating to the augmentation process or if in Transport for NSW's view (actingreasonably and in good faith) it is unlikely the parties will reach agreement on the mattersrelating to an augmentation, including after Transport for NSW has rejected anaugmentation proposal. Termination payments - Transport for NSW termination events, voluntary termination and termination for augmentations If the SLR Project Deed is terminated by Transport for NSW for its sole convenience, as aresult of a 'Transport for NSW termination event' or in connection with an augmentation,Transport for NSW will pay OpCo:(a) an amount equal to the senior debt as at termination, subcontractor breakage costs,amounts due and payable by Transport for NSW to OpCo and employee redundancypayments, which have been or will be reasonably and properly incurred as a directresult of the termination; and(b) if the termination date occurs prior to completion, the net present value, discountedto the date the termination payment is paid, of all dividends and other distributions,interest and principal payments forecast to be payable to equity contained in thebase case financial model, using the prevailing market discount rate for availabilitytype projects with a similar risk profile determined by an independent expert; or(c) if the termination date occurs after completion, the fair va lue of equity reasonablydetermined by an independent expert,Contrac t summary 1 Sydney Light Rail Project Page 43Transport for NSW ~: (d) amounts owed by OpCo to Transport for NSW, any gains which have or will accrue toOpCo as a result of the termination and not included in the termination senior debt,insurance proceeds, amounts held in certain bank accounts and the securitisationrefund payment.If either termination payment calculated above is less than the senior debt at termination,then the termination payment will be deemed to be equal to the senior debt at termination.Termination for uninsurable risk or force majeure Transport for NSW may terminate the SLR Project Deed following the occurrence of anuninsurable risk, if: (a) OpCo and Transport for NSW are unable to reach agreement on appropriatemeasures to mitigate the risk; and(b) the uninsurable risk causes material damage, loss or destruction to the Sydney LightRail or the SLR Works and the insurance proceeds that would have been payable hadthe relevant insurance continued to be available exceeds $100 million.Alternatively, Transport for NSW or OpCo may terminate the SLR Project Deed followingthe occurrence of a force majeure event, if:(a) the parties are unable to agree on appropriate measures to mitigate the effects ofthe force majeure event and facilitate the continued performance of the SLR ProjectDeed on or before the date falling 20 business days after the occurrence of the forcemajeure event; and (b) the force majeure event is continu ing or its consequence remains such that theaffected party has been or is unable to comply with a material part of its obligations.Termination payments - uninsurable risk or force majeureIf the SLR Project Deed is terminated for an uninsurable risk or force majeure, Transportf or NSW will pay OpCo:(a ) an amount equal to the senior debt at termination, 50% of the voluntary terminationequity value, amounts due and payable by Transport for NSW to OpCo and certainsubcontractor breakage costs,~: (b) any gains which have or will accrue to OpCo as a result of the termination and notincluded in the termination senior debt, amounts owed by OpCo to Transport forNSW, insurance proceeds, amounts held in bank accounts and the securitisationrefund payment.If any termination payment, is zero or a negative number, the negative number will bedeemed to be zero, Transport for NSW shall have no obligation to make any payment toOpCo and Transport for NSW shall be released from all liability to OpCo for breachesand /or termination.23. Contractual remedies available to the CrownTransport for NSW will have a number of different contractual remedies available to itshould OpCo default on its obligations related to the SLR PPP, or should Transport for NSWterminate the SLR Project Deed.Contract summary 1 Sydney Light Rail Project Page 44~'k NSW GOV!ASMENTTransport for NSW State step-in rightsTransport for NSW is entitled under the SLR Project Deed, D&C Contract Side Deed, O&MContract Side Deed and Alstom Maintenance Subcontract Side Deed, to step-in andeffect ively assume OpCo's rights and obligations under the re levant agreement, see section2 4 (State step-in rights) of this report.Indemnity OpCo inde mnifies Transport for NSW, Roads and Maritime Services, the State and othercontractors (Indemnified Party) from and against any loss incurred by an IndemnifiedParty in respect of:(a) damage to, loss or dest ruction of, or loss of use of any property belonging to anInd emnified Party or any claim against an Indemnified Party in respect of any il lness,personal injury or death of any person caused by, arising out of, or as a consequenceof any act or omission of OpCo;(b) any breach or fa ilure to comply with the terms of any proj ect agreement by OpCo orany fraudulent, negligent or wrongful act or omission by OpCo; or(c) any claim by a third party against an Indemnified Party arising out of, or in any wayin connection with, any breach or failure to comply with the terms of any projectagreement by OpCo or any fraudulent, negligent or wrongful act or omi ssion byOpCo. T he indemnity provided by OpCo under the SLR Project Deed is reduced and limited inc ircumstances agreed between the parties, including where the loss is caused by, arisesout of, or i n any way in connection with a breach by Transport for NSW. In addition, OpCohas no liability to an Indemnified Party in relation to consequential or indirect loss (subjectto speci fic exceptions).Sue for breachIf OpCo breaches any of the Tra nsport for NSW Project Agreements (other than a breachby OpCo of an obligation which results in a Service Payment Deduction), Transport forNSW may , in addition to, or as an alternative to any of the rig hts or remedies available toTransport for NSW under the Transport for NSW Project Agreements, sue OpCo or exerciseany other cont ractual or other legal or equitable rights it holds against OpCo, including (ifrelevant and avai lable) its rights under any bank securities and/or its rights under theTfN SW Deed of Charge (OpCo) or TfNSW Deed of Cha rge (Fi nance Co). Any delay oromissio n by Transport for NSW in the exercise of any right, power or remedy will notimpair such right, power or remedy or constitute a waiver of the relevant breach .Civil penalty prov isionsT ransport for NSW may enforce civil penalty provisions for the purposes of section 38 ofthe Passenger Transport Bill 1990 (NSW) where OpCo has failed to comply with certainasset management obligations and performance standards in relation to the ServicePayment - see section 17 (Price) of this report for more detail on the Service Payment.Set -off rightsTransport for NSW has the right, subject to certain restrictions, to set-off or deduct anyamount due f rom Transport for NSW to OpCo under a Transport for NSW ProjectAgreement: (a) any debt or other monies due from OpCo to Transport for NSW; andContrac t summary I Sydney Light Rail Project Page 45Transport for NSW (b) any claim to money which Transport for NSW may make in good faith against OpCowhet her for damages or otherwise and whether or not the amount is disputed .OpCo does not have these same set-off rights.Bonds In addition to the securities granted to Transport for NSW under the Deeds of Charge givenby OpCo, Finance Co and the O&M Contractor, OpCo must give Transport for NSW anunconditional bond (Handback Security Bond) to secure the performance of OpCo'shandback obligations under the SLR Project Deed. This Handback Security Bond must beprovided at least 18 months before the original expiry date of 16 March 2034. If OpCo failsto comply with this requirement, OpCo will not be in breach of the SLR Project Deed butTransport for NSW may withhold a specified amount from each monthly Service Paymentfor up to ten months.If the term of the SLR PPP is extended - see section 12 (Contract term and asset t ransfers)of this report - OpCo must prov ide an additional unconditional bond (Extension SecurityBond). If OpCo fails to provide the Extension Security Bond this will not be a breach of theSLR Deed however Transport for NSW may elect:( a) to direct OpCo to implement the extension, and if the parties are unable to reachagreement either party may refer the matter to dispute resolution - see section 28(Dispute resolution) of this report; or( b) that the term of the SLR Project Deed will expire on the original expiry date of 16March 2034.Application of p roceedsTransport for NSW may only apply the proceeds of :(a) the Handback Security Bond (or any security withheld) towards payment of anyamount due from OpCo to Transport for NSW as notified by the final inspectionaud itor; and(b) the Extension Security Bond to reimburse Transport for NSW for any loss for whichOpCo is liable or payment or other moneys owing by OpCo to Transport for NSWafter the original expiry date.Service Payment deduction Transport for NSW has the right to deduct amounts from the Service Payment if OpCo failsto meet service requirements - see section 17 (Price) of this report for further detail on theService Payment.24. State step-in rights SLR Project Deed Transport for NSW will have a right to step in to the role of OpCo and assume OpCo'sser vice delivery obligations under the SLR Project Deed on the occurrence of:( a) an 'OpCo termination event'; or( b) an event or circumstance which arises out of or in connection with OpCo's activitieso r the SLR PPP that poses a serious threat or cause material damage or disruptionto: C ontract summary 1 Sydney Light Rail Proj ect Page 46Transport for NSW (i) the health or safety of persons;(ii) the environment;( iii) any property; or(iv) the safe and secure performance of OpCo's activities.On the occurrence of an event which triggers step-in rights and provided adequate notice isgiven in accordance with the SLR Project Deed requirements, Transport for NSW may doanything that OpCo could do in respect of OpCo's obligations including: (a) enter into and remain in possession of all or any of the assets;(b) operate and manage all or any of the assets;(c) ex ercise all or any of OpCo's rights, and perform all or any of OpCo's obligations inconnection with OpCo's activities, the project agreements (other than a debtfinancing or equity document) or under any accreditation or approval held by OpCo, as if it were OpCo, to the exclusion of OpCo;(d) do anything Transport for NSW (or its nominee) considers necessary or desirable toremedy the step -in event or overcome the risk or mitigate any consequences of thestep-in event; and (e) do anything incidental to the matters listed above.During the step -in period, OpCo and Transport for NSW must comply with certaincoope ration obligations as outlined under the SLR Project Deed.Where Transport for NSW has exercised its step-in rights and OpCo continues to performobligations under the SLR Project Deed which affect the calculation of the Service Payment,Transport for NSW will pay OpCo based on actual performance of those obligations and ifOpCo 's performance of obligations is suspended, the parts of the Service Payment affectedby the step-in based on the average performance of OpCo for the 6 months immediatelyprior to step-in, less:(a) if the step-in event was an 'OpCo termination event':(i) costs avoided by OpCo as a result of Transport for NSW exercising its step-inrights ; and( ii) the reasonable costs incurred by Transport for NSW in exercising its step-inrights; or(b) if the step-in event was not an 'OpCo termination event', the costs avoided by OpCoas a result of Transport for NSW exercising its step-in powers.Transport for NSW must cease to exercise its step-in powers as soon as reasonablypract icable and, in any event, upon the earlier of the step-in event being remedied orTransport for NSW notifying OpCo in writing that it will no longer exercise its step-inpowers .D&C Contract Side Deed and O&M Contract Side Deed Under the D&C Contract Side Deed and O&M Contract Side Deed, Transport for NSW maystep-in where OpCo is in breach under the D&C Contract or O&M contract (as applicable)and take steps to remedy the default if the respective contractor has given Transport for NSW a cure notice of the default and confirmed that either:Contract summa ry I Sydney Light Rail Project Page 4725. Transport for NSW (a) the cure or remedy period available to the debt financiers in respect of the defaultevent under any debt financing document has expired without a cure or remedybeing achieved or the Security Trustee has notified the relevant contractor that itdoes not intend to cure the default ; or(b) the relevant contracto r's right to terminate, rescind, accept the repudiation of, orsuspend the performance of any or all of its obligations under, the relevant side deedis not subject to any right of the debt financiers to cure or remedy the default event.If Transport for NSW does step-in:( a) OpCo obligations (other than OpCo's obligation to pay the relevant contractor) aresuspended to the extent and for such period as OpCo is prevented from performingsuch obligations as a result of the step- in;(b ) Transport for NSW may, after giving OpCo reasonable prior notice, cease to exerciseits step-in rights once the relevant default event has been remedied; and(c) OpCo must compensate Transport for NSW for any reasonable loss suffered orincurred as a result of the step in.Alstom Maintenance Subcontract Side Deed Under the Alstom Maintenance Subcontract Side Deed, Transport for NSW may step-in forany default by the O&M Contractor under the Maintenance Subcontract or any event orcircumstance which wou ld entitle Alstom to terminate, rescind, accept the repudiation of,or suspend any or all of Alstom's obligations under the Maintenance Subcontract, providedthat A lstom has given Transport for NSW a default event notice and complied with certainconditions If Transport for NSW does step-in:(a ) the O&M Contractor's obligations are suspended to the extent and for such period asthe O&M Contractor is prevented from performing such obligations as a result of thestep-in; (b) Transport for NSW may, after giving the O&M Contractor reasonable prior notice,cease to exercise its step-in rights once the relevant default event has beenremedied; and (c) the O&M Cont ractor must compensate Transport for NSW for any reasonable losssuffe red or incurred as a result of the step in.Transition out provisions Transport for NSW has the r ight to, on or before the expiry or termination of the contractterm, invite any person to perform all or part of OpCo's activities for the periodcommencing after expiry or termination of the contract term . As such, OpCo must manage,perform and maintain OpCo 's activ ities in a way that an appropriately qualified andresourced step in party, successor or nominee of Transport for NSW is able at any time toimmed iately take over the performance of OpCo's activities without interruption.OpCo must at its own cost, do everything (both before and after expiry or termination ofthe contract term) that is reasonably required by Transport for NSW to assist a successoror nominee of Transport for NSW in performing OpCo's activities, and must not do anythingthat directly or indirectly avoids or materially prejudices or frustrates the transfer of theperformance of OpCo's activities.Cont ract summary I Sydney Light Rail Project Page 48Transport forNSW Preparation for contracting at end of term OpCo must provide Transport for NSW with reasonable access to staff and to information,books and records kept by or on behalf of OpCo in connection with the SLR PPP, for thepurpose of Transport for NSW preparing reports and documents in connection with anyinvitation to a person for the performance of OpCo's obligations. OpCo must usereasonable endeavours to assist Transport for NSW in the preparation for, and .conduct of,a fair and competitive expression of interest or tendering process.Access OpCo must, without unduly interfering with OpCo's obligations, ensure that a prospectivesuccessor, successor or nominee of Transport for NSW has access to the assets, light railmaintenance and stabling facilities and certain employees for the purposes of theprospective successor, successor or nominee of Transport for NSW receiving informationabout OpCo's obligations and preparing to take over the performance of those obligations. Required employees OpCo's ability to vary the employment contracts of certain employees involved in theoperation and maintenance of the Sydney Light Rail is limited in circumstances where thevariation takes effect in the 12 months prior to expiry of the term or will first take effectafter the end of the contract term and Transport for NSW's prior approval is generallyrequired. At the expiry of the contract term, Transport for NSW must procure that asuccessor makes offers of employment to these employees on terms which are similar toand are, on an overall basis, no less favourable than their terms of employment with OpCo(or the O&M Contractor).Novation OpCo must procure the novation to Transport for NSW or its nominee of, or execute any document required to effect OpCo ceasing to be party to, any subcontract relating toOpCo's activities which Transport for NSW may nominate in its absolute discretion witheffect from the end of the contract term or such other date as Transport for NSW mayagree. Documents OpCo must deliver to Transport for NSW or its nominee (or both if required) all and anydocuments and information concerning OpCo's activities which are required for the efficienttransfer of responsibility for their performance, including drawings, plans, manuals,software designs, reports, computer records, specifications, calculations, designdocumentation, documentation relating to intellectual property, and any otherdocumentation specified under the SPR.26. Transfer of land and assets by the public sector to the contractor Land and fixed assets All fi xtures affixed to the Sydney Light Rail site will be owned by Transport for NSW fromthe time they are affixed. Transport for NSW grants OpCo a non-exclusive licence to use and occupy the constructionsite, and to permit OpCo and its contractors to use and occupy the construction site, forthe purpose of performing the delivery activities. This licence commences on the specifiedsite section access date for the relevant part of the construction site or such other dateCont ract summary 1 Sydney Light Rail Project Page 49Transport for NSW agreed between the parties, is subject to any requirements under the third partyagreements, specified third party requirements and utility provider agreements andterminates on the date of completion.Transport for NSW grants OpCo a non-exclusive licence to use and occupy the permanentlight rail corridor for the IWLR from the date of revenue service on the IWLR and thepermanent light rail corridor for the CSELR from the date of completion. This licencepermits OpCo and its contractors to use and occupy the permanent light rail corridor forthe purpose of performing the operations activities. This licence terminates at the end ofthe term. Moveable Assets All Moveable Assets will be owned by Transport for NSW. OpCo must ensure that ownershipof the Moveable Assets transfers to Transport for NSW on the date OpCo acquires t itle andin the case of chattels forming part of the SLR Works, no later than the date forcompletion. Transport for NSW grants OpCo an exclusive licence to use the Moveable Assets for thepurpose of fulfilling OpCo's obligations under the SLR Project Deed. This licencecommences on the date that ownership of each Moveable Asset transfers to Transport forNSW and terminates at the end of the term . ·Transport for NSW also grants to OpCo an exclusive licence to use the existing moveableassets on the IWLR for the purpose of fulfilling OpCo's obligations under the SLR ProjectDeed. This licence commences on the date of revenue service on the IWLR and terminatesat the end of the term.Hand back At the end of the contract term, OpCo must transfer all of OpCo's rights, title and interest( if any) in the assets to Transport for NSW (or its nominee) free from any security interestsand ensure that the assets are in a required state and condition (fair wear and tearexcepted) .27. Change of ownership and control under the SLR Project Deed The SLR Project Deed places certain restrictions on Transport for NSW and OpCo in theevent of a change in control.OpCo has undertaken that, save in certain permitted circumstances, throughout the SLRPPP it will not permit any direct or indirect changes to the legal or beneficial ownership ofits shares or units or any related body corporate ident.ified as a member of the OpCogroup, without Transport for NSW's prior written consent, which will not be unreasonablywithheld . If OpCo does not obtain Transport for NSW's consent, this will be an 'OpCoterm ination event' - see section 22 (Termination rights) of this report.OpCo must also obtain Transport for NSW's consent for changes in control, save in certainpermitted circumstances, that relate to each Core Contractor. Different consentrequirements apply depending on whether it is the O&M Contractor or D&C Contractor.OpCo is required to gain Transport for NSW's written consent prior to a change in control ofthe O&M Contractor. Failure to comply with this requirement will be an 'OpCo terminationeve nt'- see section 22 (Termination rights) of this report.Alternatively, if a change in control of an entity that is a joint venture participant in theD&C Contractor has occurred prior to completion, OpCo must promptly notify Transport forContract summary I Sydney Lig ht Ra il Project Page 50Transport for NSW NSW and obtain Transport for NSW's approval. If Transport for NSW subsequently notifiesOpCo that Transport for NSW does not approve the change in control, OpCo must within60days of receiving such notice either, terminate and re-tender the works or services,procure that the relevant entity is replaced or removed, or take such other action asagreed by Transport for NSW. Should OpCo fail to comply with these additionalrequirements, then this will be an 'OpCo termination event'- see section 22 (Terminationrigh ts) of this report.28. Dispute resolutionAll disputes between Transport for NSW and OpCo ansmg out of the SLR PPP must be resolved in accordance with the detailed procedures set out in the SLR Project Deed.Dispute Avoidance Board A dispute avoidance board (DAB) was established prior to financial close. The DAB is madeup of three members who hold regular meetings to assist Transport for NSW and OpCo toconsensually resolve issues and prevent disputes. The DAB has a proactive generaladvisory function. Either party may refer a dispute to the DAB for its opinion in accordancewith the procedure set out in the SLR Project Deed.Each member of the DAB will be required to act fairly, impartially, honestly andindependently. Transport for NSW and OpCo have agreed that they will not unilaterallycommunicate with the DAB or its members on matters dealing with the conduct of the workor resolution of problems. The parties will jointly pay for the cost of the DAB. The DABAgreement will terminate on final completion unless otherwise agreed by both parties.Dispute process The dispute resolution procedure essentially involves four elements: regular DAB meetings,negotiation, expert determination and arbitration. Throughout these processes both partiesmust continue to perform all of their obligations under the SLR Project Deed. Negotiation If a dispute arises, either party (Party A) may give the other party's representative (PartyB ) a letter of dispute. If the representatives are unable to resolve the dispute within 30business days after the date on which the letter of dispute was given, either party mayr efer the dispute to executive negotiation.The executive negotiators may, by agreement, meet together with the DAB or refer the'dispute to one of the following alternative forms of dispute resolution:(a) mediation;(b) expert determination;(c) arbitration; or(d) the DAB for its opinion.If the executive negotiators are unable to resolve the dispute (in whole or in part) within30 business days after the date on which the dispute was referred to them, Party A may, ifit wishes to pursue the dispute, issue Party B with a referral to arbitration.Arbitration If a dispute is referred to arbitration, the Australian Centre for International CommercialArbitration (ACICA) Arbitration Rules will apply and any arbitrator will have the power toContract summary I Sydney Light Rail Project Page 51Transport for NSW grant any legal, equitable or statutory remedy but not punitive damages. This process aimsto achieve a just, quick and cost-effective resolution of any dispute. Any award of thearbitral tribunal will be final and binding upon the parties.DAB opinion If a dispute is referred to the DAB, the DAB must give its opinion within 30 business days(or such other period as proposed by the DAB and agreed by the parties). Any opiniongiven by the DAB will be on a 'without prejudice' basis and will not be binding unless theparties agree in writing to be bound by it.Disputes under Core Contracts OpCo must immediately inform Transport for NSW if a dispute arises under the D&CContract or O&M Contract. Disputes under related contracts Independent Certifier Deed Any dispute under the Independent Certifier Deed relating to an amount in an accountsubmitted by the Independent Certifier will be determined by the Transport for NSWrepresentative. Any determination by the Transport for NSW representative must be giveneffect to by the parties unless and until it is reversed or overturned in any subsequentcourt proceedings. There are no other dispute resolution provisions in the IndependentCertifier Deed. Core Contract side deeds If there is a dispute between Transport for NSW and the relevant Core Contractor as tohow the terms of the relevant Core Contract are deemed to have been amended to reflectthat the SLR Project Deed is at an end, the dispute resolution process in the SLR ProjectDeed will be incorporated into the relevant Core Contract and referenc es to "OpCo" wouldbe read as if they were references to the relevant Core Contractor.Financiers Tripartite Deed Disputes between Transport for NSW and the Security Trustee in relation to the contents ofthe step-in report (which is a report produced and agreed between Transport for NSW andthe Security Trustee upon receipt of a step-in event notice) may be referred for resolutionin accordance with the SLR Project Deed as if the clause was incorporated into theFinanciers Tripartite Deed and a reference to "OpCo" was a reference to the SecurityTrustee. There are no other dispute resolution prov1s 1ons in the Financiers Tripartite Deed .Accordingly and subject to the SLR Project Deed, any other disputes under the Financiers Tripartite Deed are to be resolved by the Courts of NSW.Equity Purchase Deed Disputes arising out of the Equ ity Purchase Deed must be resolved in accordance with thedispute procedures set out in the Equity Purchase Deed . The parties to the dispute musteach appoint a representative to meet and discuss the matters raised in a dispute noticeand genuinely make an effort to negotiate agreement on such matters . If the matter is notagreed within a 10 day period, either party may refer the outstanding matters to an expertfor determination . The expert's decision, in the absence of manifest error, will be final andbinding on the parties unless a party gi ves a notice of dissatisfaction within 10 days of thedetermination and refers the matter to arbitration. Any matters referred will be finallysettled in accordance with the lAMA Rules for the Conduct of Commercial Arbitrations.Contract s ummary I Sydney Light Rail Project Page 5229. Transport forNSW Insurance OpCo insurance requirements OpCo must effec t and maintain de livery and operations insurances for amounts anddeductibles, and for the duration, as set out in the SLR Project Deed. OpCo's obligations inre lation to insurances for the SLR PPP include:(a) not knowingly do or permit, or omit to do, anything which prejudices any insurance;(b) rectify anything which might prejudice any insurance;(c) reinstate any insurance if it lapses;(d ) not cancel, vary or allow any insurance to lapse without prior written consent fromTransport for NSW;(e) immediately notify Transport for NSW of any fact or circumstance, including achange, which may prejudice an insurance; ( f) give full and true particular information to the insurer of all matters;(g) notify Transport for NSW of all claims and keep Transport for NSW informed ofsubsequent developments; (h) comply at all times with the terms of each insurance.Review and benchmarking Transport for NSW will review the minimum sums insured and deductibles for all operationsphase insurances on each anniversary of the date of completion to determine any increaseor decrease . Any change will be subject to the insurance benchmarking regime.Insurance proceeds Subject to the terms of the Financiers Tripartite Deed, OpCo must deposit all insuranceproceeds received in respect of the costs of replacement, reinstatement or indemnity valueof the SLR Works or the Sydney Light Rail into an insurance proceeds account.This money, with certain exceptions where the SLR Project Deed is terminated early or theinsurance proceeds are paid to Roads and Maritime Services, must only be applied by OpCoto promptly reinstate or repair the damage. If Transport for NSW requires OpCo toreinstate or repair the SLR Works or the Sydney Light Rail on the basis of differentspecifications by directing a modification, available insurance proceeds will be taken intoaccount in calculating the net financial impact of the modification.30. Liabilities, indemnities and guarantees given by the Crown Indemnities given by Transport for NSW Transport for NSW has promised various indemnities under the Transport for NSW ProjectAgreements. These indemnities are briefly summarised be low.(a) Liability for reinstatement: Transport for NSW must pay OpCo the reasonable costof carrying out the reinstatement or repair work (to the extent insurance proceedsContract summary I Sydney Light R ail Project Page 53Transport for NSW are insufficient) to the extent that loss, damage or destruction arises out of war orarmed conflict in each case occurring within Australia, chemical or biologicalcontamination, ionising radiations or contamination by radioactivity in case occurringin Australia and not caused by OpCo or its contractor, a breach of any Transport forNSW Project Agreement by Transport for NSW and any fraudulent, negligent or otherwrongful act or omission of the State, Transport for NSW or their associates.(b) Liabilities for taxes, rates and stamp duty: Transport for NSW will pay andindemnify OpCo and any parties to the debt financing documents against, andreimburse OpCo and any parties to the debt financing documents for, all duty(including penalty, fine, charge or interest payable) in respect of the Transport forNSW Project Agreements, debt financing documents or any document or transactionexpressly contemplated by them, subject to certain exclusions.(c ) Liability for rates and land tax: Transport for NSW must pay and indemnify OpCoand Finance Co against all rates and land tax in respect of the Sydney Light Rail siteuntil the end of the contract term.(d) Liability for third party software licences: Transport for NSW must indemnifyOpCo against all claims in respect of third party. software licences that occur whereTransport for NSW has required OpCo to assign, sub-licence or novate to Transportfor NSW any rights and obligations of OpCo in respect of third party softwarelicences. Transport for NSW will indemnify OpCo on or from the date of assignmentor novation of such third party software licences.(e) Liability under the Dispute Avoidance Board Agreement: Transport for NSWand OpCo have agreed to each indemnify each DAB Member under the DABAgreement against all claims from a person not a party to the DAB Agreement forany act or omission done in good faith and with due care and diligence.(f) Liability under the City of Sydney Development Agreement: Transport for NSWi ndemnifies the City of Sydney (City), the City's employees and electedrepresentati ves of the City from and against all third party claims brought against,suffered or incurred by the City, the City's employees or its elected representativesto the extent arising out of the use or occupation of the site by Transport for NSW orits employees or agents, the relocation, removal, modification or protection of theCity's utilities, the design, construction, installation, upgrade or relocation of certainCity assets or any negligent act or omission of Transport for NSW or its employees oragents in relation to, or as a consequence, of the project.Guarantees given by the Crown The "PAFA Act Deed Poll of Guarantee" executed by the NSW Treasurer (on behalf ofthe State of NSW) in favour of OpCo and the Security Trustee (the Beneficiaries) dated17 December 2014, provides a guarantee by the State of NSW to the Beneficiaries inaccordance with section 22B of the Public Authorities (Financial Arrangements) Act 1987(NSW), of Transport for NSW's performance of its payment obligations under the SLRProject Deed, the Financiers Tripartite Deed, the Receivables Purchase Deed, the PaymentDirections Deed , the Equity Purchase Deed and any other documents approved in writingby the NSW Treasurer in the future.31. Significant guarantees and undertakings The SLR PPP contains a number of guarantees and undertakings. Below is a brief summaryof the significant guarantees between the parties.Contract summary I Sydney Lig ht Rail Project Page 54Transport for NSW PAFA Act Guarantee As mentioned in section 30 (Liabilities, indemnities and guarantees given by the Crown),the State guarantees the performance of Transport for NSW's payment obligations underthe SLR Project Deed and other documents.D&C Guarantee Each D&C guarantee is an irrevocable guarantee given by each D&C guarantor to OpCo toguarantee all liabilities and obligations of that D&C guarantor's subsidiary that arises out ofor in connection with the D&C Contract, and to indemnify OpCo against any loss arisingfrom any failure by its subsidiary to perform any of its obligations.O&M Guarantee The O&M guarantee is an irrevocable guarantee gi ven by the O&M guarantor to OpCo toguarantee all liabilities and obligations of the O&M Contractor that arise out of or inconnection with the O&M Contract, and to indemnify OpCo against any loss arising fromany failure by the O&M Contractor to perform any of its obligations.Contract summary I Sydney Light Rail Project Page 55Transport for NSW Appendix 1 Glossary of terms Moveable Assets means the CSELRVs, spares, special tools and equipment, non-revenue ve hiclesand other chattels forming part of the SLR Works or used by OpCo or OpCo's contractors for thepurpose of carrying out OpCo's activities.Service Payment means the monthly availability payment made by Transport for NSW to OpCounder the SLR Project Deed .SLR Works means the physical works, assets, systems and deliverables that OpCo must design andconstruct under the SLR Project Deed .Sydney's Light Rail Future means the publication titled "Sydney's Light Rail Future - ModernisingSydney 's Trains" dated June 2012 by the NSW Government.Contract summary I Sydney Light Rail Project Page 56 |
|
|