-
Buses were blamed for
Sydney's traffic congestion
Unfair - cars deserve the blame.
The buses were delayed by the cars. Before buses were removed, did
you ever see the George St entertainment area on Friday evenings at about
6pm? Inbound buses could barely move even though they were going in the
opposite direction to the official peak and were less numerous than in peak.
We should have removed the cars first.
- Light rail's capacity to handle A.M. peak-hour loads
Diagram of CBD entry routes and loads from page 12 of
Sydney City Centre Access Strategy
In the Environmental Impact Statement ("EIS") for the Sydney CBD &
South-East Light Rail project ("CSELR"), Transport for New South Wales
("T4NSW") claimed the ultimate capacity to be 30 trams × 300 pax = 9000 pax
each way per hour. That was a serious exaggeration. A more useful figure
would have been 24 48-metre trams × 250 pax = 6000 pax each way per hour.
The initial capacity in 2019 was 20 trams × 250 pax per hour = 5000 pax each
way per hour of which only 1600 pax had seats however subsequent
announcements foreshadowed a rise in capacity. The
Alstom website shows that typical configurations provide seats for less
than 30% of the passenger capacity. The 466 passengers claimed for 67-metre
trams should likewise be discounted to 400 with just 96 seated (the 24
hinged seats are assumed to be in the folded-up position, each making room
for 2 passengers to stand rather than for one to sit).
The claimed capacity for 30 trams
per hour each way seems unachievable at peak hour, just when it would be
needed. That number of trams would require the major intersections on the
route (Bridge/George/Grosvenor, Elizabeth/Devonshire, Anzac/Cleveland) plus
the Alison Road crossings to be interrupted up to 60 times per hour for a
tram to cross. Co-ordinating the inbound and outbound trams reliably and
thereby holding the disruptions down to 30 times per hour would be
impossible. See remarks below about interference with cross traffic.
Whether that capacity would be enough for the load in the morning peak is
academic. The actual capacity will be much less - at most 6000 before
overcrowding becomes unacceptable. The inbound trams will be overloaded as
they approach the Chalmers St stop. Worse, many passengers entering the CBD
on Broadway buses would find a tram ride up George St preferable to a slower
and longer bus trip along Elizabeth St. These passengers could be expected
to transfer to tram at Rawson Place however there probably won't be enough
room for them.
The situation might be even worse than that. There seem to be grounds for
suspecting the EIS figures were massaged to downplay the overcrowding. For
instance, the EIS statistics were presented in whole hours, possibly masking
a greater peak between perhaps 0740 and 0840. In any case, there will
inevitably be fluctuations in trams' loadings depending on how many busloads
they receive at Randwick or Kingsford, making crowding in some of the trams
even worse than averages would suggest.
Worse again, the EIS showed that the planned Kingsford leg will attract
more passengers than the Randwick leg. This imbalance will exacerbate the
overcrowding on half the services.
About 40 public submissions to
the EIS vainly questioned CSELR's capacity. Peter Mills' submission looks at
several aspects of capacity. The official story that capacity was adequate
changed on 23 October 2014 when a ministerial announcement said "the biggest
challenge for this project is meeting the high demand" and went on to
foreshadow a substantial increase in capacity although by unspecified means.
On 18 December 2014 another ministerial announcement lengthened the trams
from 48 metres to 67 metres but was vague about what this meant for
capacity.
The eventual agreement with Alstom was for a maximum of 15 services per
hour each way along George St, one every four minutes. That means one tram
each way every eight minutes on each of the Kingsford and Randwick legs.
Assuming the claimed capacity of 466 passengers per tram, 15 x 466 = 6990
pax per hour. That capacity would be barely enough for the peak-hour figures
shown in the 2012 diagram above. The demand encountered in 2019 will be
more. Further, there should be an allowance of perhaps 20% for fluctuations
in demand. So not all the 2019 passengers will fit within the available
capacity. Presumably the rest will be accommodated in extra peak-hour
express buses and/or squashed onto trams at more than 4 per square metre.
The 15 trams per hour will have at most only 120 seats each (96 fixed and 24
flip), so only 15×120 = 1800 of the passengers can ever be seated.
Here is Table 29 from page 33
of Transport for NSW's capacity planning guidelines dated December 2013:
If you're not sure what four passengers per square metre would be like, look
at this video.
Obviously, loading six adults per square metre would not be popular but the
authorities nevertheless expect it to happen. Note that more passengers are
using hand-held electronic devices than formerly and this requires more room
and for many people requires a seat. The official standards could therefore
need review.
Just for comparison, the seated capacity of the replaced bus services
(the EIS says 220 morning peak hour buses won't have to enter the CBD) would
be at least 45×220 = 9900 seats.
Developments in the pipeline stand to increase the local population, and
hence increase the demand for transport, substantially. For example, a
proposed development of 750 home units on the former Inglis stables site has
been approved. There will be other approvals.
-
Long-term disruption to
bus services
Pursuant to a 2013 plan called
Sydney
City Centre Access Strategy from 4th October 2015 all George St
buses (including those that use the Anzac Bridge) were diverted. Many now
use Elizabeth St to travel to Circular Quay; some go elsewhere. Elizabeth St
is presumably now a slower trip than at present because Elizabeth St was
already congested and would have become more congested with the extra
traffic. These detours will continue through the construction and testing
phases of the CBD and south-east light rail project - at least three years.
Once the CBD and south-east light rail service has settled down in
perhaps late 2020, all of the former George St bus services will be altered
to either terminate at Haymarket or else leave the city in other directions.
All passengers wishing to ride further into the CBD beyond Haymarket will
have to transfer to light rail.
However, the northbound light rail vehicles arriving at Haymarket will
already be carrying passengers from the south-eastern suburbs and will
probably be unpleasantly crowded in peak hour.
Please note that the Sydney City Centre Access Strategy is officially a
quite separate plan from the CBD and south-east light rail and therefore
no-one in authority will admit that it is a consequence of the light rail
decision. The strategy has a rather Orwellian view of transport - for
example, its December 2015 update says the disruptive 4 October changes were
to "improve the way we use our city centre".
-
Barangaroo and other
construction disruption
We don't know much because Transport for NSW hasn't released any
analysis. But we do know that they are concerned - in a submission on the
proposed Barangaroo casino T4NSW says "the changes to George Street in the
Sydney CBD when light rail is built there will increase traffic movements on
the road work located within and adjacent to the Barangaroo project". See
http://www.smh.com.au/nsw/barangaroo-casino-parking-traffic-concerns-raised-by-transport-for-nsw-20150515-gh2cpo.html.
-
P.M. peak on the light
rail
Post-COVID, Broadway-bound passengers from around
Wynyard will quickly fill available space in southbound George St trams
because they will thus get to Rawson Place sooner than Elizabeth St buses
can take them. Eastern suburbs passengers will therefore find boarding
difficult around Town Hall and will be delayed waiting for a tram which can
carry them.
-
Students
Doubt has been expressed whether the A.M. peak
service can handle the combined outbound load of SBHS, SGHS and UNSW
passengers. And the principal of SBHS has expressed concern that an
afternoon peak of returning USNW students might load trams to the point
where some high-school students are unable to board.
A count made in Albion St on 28 August 2014 found over 3600 passengers on
891 (UNSW) and 610 (SBHS, SGHS) riding between 8 a.m. and 9 a.m. Even
without any passengers for other destinations, not many of the students can
expect seats on trams - there will be at most only 1800 seats per hour.
Especially in the morning peak, there will be situations where adults and
schoolchildren are standing together in tightly-packed trams. Parents might
well be reluctant to let their children ride in these conditions.
Learn more...
-
Standing room
T4NSW figures seem to rely on four standing passengers per square metre
of floor space. If you can't visualise that, think of a fully-loaded lift in
which people stand at about that density for a few seconds per trip. What if
most of those people are students with backpacks?
-
Obfuscation
How many buses do the trams
replace? The June 2014 video says 220 - see
http://www.youtube.com/watch?v=pUQoV8DPkNI. If that means 220 per
morning peak, which routes are they? The EIS nominates several routes which
are to remain bus but points out that the list might change. There aren't
220 buses in the other south-eastern routes.
Table 2-1 (EIS Technical
Paper 1, page 39) lists services under study, including express services.
EIS Section 4.2.2 provides an
overview of possible bus service changes. Some bus routes are to continue to
operate into the CBD. However, the Cleveland/Crown district will lose most
of its bus services yet be well away from light rail.
Sydney's Light Rail Future
(dated December 2012, page 18) provides further information but may be
out-of-date. The figure of 220 buses shown above is close to the 227 shown
on page 18 but that 227 includes 55 Harbour Bridge services!
About 1084 scheduled buses
arriving from Broadway pass through Railway Square each weekday, 159 of them
between 8 a.m. and 9 a.m. These figures do not include red metrobuses M10
and M30 (six of each per peak hour). Nor do they include L88 and L90 etc.
buses and Hillbus services which join George St further north.
Bus volumes, from page 18 of Sydney's Light Rail Future
(Dec. 2012)
-
Speed
Sydney public transport is
too slow and is not getting faster. Many rail services, including the
Dulwich Hill light rail, could and should be run at higher speeds. Professor
Hensher has published
research showing that replacing M2 buses by feeders to Sydney Metro
North-West would result in longer trip times to the CBD from most of the
north-west.
CSELR speeds as envisaged by the EIS
will also be unacceptably slow. For example, 15 minutes from Central to
Circular Quay compares very unfavourably with heavy rail, which can do the
whole city circle from Central to Circular Quay to Central with 5
intermediate stops in about 13 minutes. CSELR's slowness is probably due to
insufficient priority over crossing traffic.
The popular trip from Central to
UNSW is also likely to be slower in CSELR trams than in existing express
buses.
It has been pointed out that, based
on a number of European examples plus the Gold Coast Linq and noting the
relatively low number of CSELR stops, that a trip of 8.5 km from Circular
Quay to the end of either CSELR branch should take about 22-23 minutes and
certainly no more than 25 minutes. T4NSW estimates have been considerably
longer - about 35 minutes. This discrepancy can only be explained by lack of
traffic light priority.
The former trams withdrawn in
the 1950s got between Circular Quay and Central in 15 minutes with 12
intermediate stops (one at nearly every intersection). CSELR is projected to
take 15 minutes over this section with only 5 intermediate stops. Again, the
only reason can be lack of tram priority at traffic lights on cross streets.
-
Variability of speed
has consequences
Some trams will get lucky and encounter a series of green lights.
Unfortunately, that doesn't mean they'll be much quicker. Unless the tram in
front has been equally lucky, the fast tram might find itself running up
against the earlier service. It will have to slow down, not only because
overtaking is impossible but also because the tram stops can only handle one
vehicle at a time.
-
Light rail interference
with cross traffic
Light rail vehicles typically accelerate and brake at about 1 metre per
second per second. Any more is uncomfortable to standing passengers and is
likely to result in passenger falls inside the vehicle. The
Alstom website shows maximum braking and acceleration are both 1.2
metres per second per second for the Citadis X05.
This has particular significance for cross traffic. For example, the
offset Bridge/George/Grosvenor intersection spans 55 metres of George St. A
67-metre light rail vehicle must therefore travel 55 + 67 = 122 metres to
clear that intersection. This may well be from a standing start if the
traffic signals were against the vehicle when it arrived. And southbound
vehicles will have to stop immediately after clearing Grosvenor St. Let us
optimistically assume the vehicle starts immediately it gets a green light,
accelerates at full power and brakes at maximum, and that the traffic
signals change to favour cross traffic immediately after the vehicle has
cleared the intersection. Formulę taught in high school show that about ten
seconds is required for acceleration during which the vehicle travels 61
metres. Another 10 seconds is required to decelerate over a further 61
metres. So just over 20 seconds will be required for each vehicle to cross.
In practice, each interruption to Bridge/Grosvenor traffic would be rather
more than 20 seconds.
Grosvenor St is a major feeder to the Sydney Harbour Bridge and will
increasingly carry Barangaroo traffic. Its importance to Harbour Bridge
traffic was amply demonstrated on 5 January 2015 when an unplanned closure
of the Bridge/George/Grosvenor intersection in peak hour resulted in buses
and cars backed up across the Bridge to North Sydney, despite the light
holiday traffic.
There are several other intersections where conflicts between light rail
and other traffic are likely to be an issue at peak hour.
-
What's wrong with long
trams?
All of the stops, and some city blocks, are too short to contain more
than one 67-metre light rail vehicle. Some city blocks are too short to
contain even one light rail vehicle. Therefore the vehicles cannot travel in
clusters and can only cross intersections one at a time. This reduces the
number of LRVs that can be run each hour.
Infrastructure NSW prepared a State Infrastructure Strategy "First Things
First" in 2012 which stated that using 60-metre trams was not considered
feasible in Sydney's CBD as it would be too obstructive for retail
loading/access points (page 98). What about 67-metre trams?
-
Breakdowns and special
events
Bus services are readily diverted when large crowds, such as New Year's
Eve, preclude the ordinary route. Parades (e.g. Anzac Day) and breakdowns
are also handled by diverting buses. The light rail service must cope with
these contingencies which it can only do by turning vehicles back before
they reach Circular Quay. It might have to do the same in peak hour due to
heavy cross traffic at Grosvenor and Bridge.
An incident on 25 February 2016, in which police closed Eddy Avenue for
three hours to all road traffic and also stopped the light rail service
which crosses Eddy Avenue, highlights the vulnerability of rail services to
blockages. Buses were diverted away from Eddy Avenue during this incident
but were otherwise able to operate. CSELR light rail services would have
been cut at Central for the whole duration of the incident.
Gold Coast light rail services are prone to disruption too - see, for
instance,
http://www.brisbanetimes.com.au/queensland/gold-coast-trams-suspended-after-collision-20161009-gry5sm.html.
And on 15 January 2017, a tram derailed after striking a fire truck,
blocking both tracks. If the derailed tram had travelled one metre further,
it would have struck a pole which supported overhead power lines.
-
George St mall
A strategy to turn George St into "Sydney's major boulevard and a
world-class destination for walking, shopping and dining" was published in
draft as
George St 2020. It is unrealistic - the authors have overlooked
such boring details as maintaining essential access for daily shop
deliveries, occasional heavy deliveries and emergency vehicles.
-
The road network
Apparently T4NSW has found by modelling that giving the trams the
priority they need at junctions like Cleveland St, Anzac Pde and Lang Rd
could result in serious detriment to traffic conditions over a wide area. No
announcement has been made but modelling released in response to a GIPA
request showed that, without traffic signal priority, a service level of 15
trams per hour would see some trams catching up with the tram in front.
Learn more....
Any increase in tram numbers would greatly worsen the bunching effect. No
doubt this is why the service level of 15 trams per hour was chosen.
-
Lost parkland
Sydney has a long history of parkland being filched for other purposes.
This can happen gradually over many years. While sport might seem a valid
reason for appropriating parkland, consider the case of Wentworth Park
(between Pyrmont-Ultimo and Glebe), much of which is now a greyhound track
and associated grandstands.
Further west, the eastern corner of Parramatta Park was long ago handed
to the Parramatta Leagues Club. Fans celebrating the club's premiership win
in 1981 started a fire which destroyed the old Cumberland Oval grandstand
nearby. The club then wanted to replace the oval by a 40000-seat stadium.
Both the local council and the park trustees approved however the project
was limited by the Land and Environment Court. Twin grandstands were erected
and became known as Pirtek Stadium. They were demolished early in 2017. The
club is expanding Pirtek to surround what was once a parkland oval. The
adjacent Parramatta Swimming Centre (opened 1959) and associated car parks
also stand on former parkland. At the south corner, so does Parramatta RSL
Club. The swimming centre site will be absorbed by the Pirtek expansion.
Note that in 2001 the proposed Epping-Chatswood rail bridge across the
Lane Cove River was to be approved on the condition that there be a land
swap for lost parkland, even though the affected land already had a busy
road bridge across at the same point. (The Parramatta Rail Link was
approved in February 2002, passing under the river in a tunnel and hence not
requiring parkland.)
Returning to CSELR, the following parks have been affected by the
project:
- Ward Park lost a strip.
- Wimbo Park lost a wide strip but gained land from the former
Olivia Gardens site.
- Moore Park East lost a wide strip.
- Tay Park lost a strip.
- Centennial Park lost a strip parallel to the existing busway.
- High Cross Park stood to lose a wide strip of grass and all
its trees. It contains the major war memorial for the Randwick district
and has attracted large crowds on Anzac Day. Although the parkland loss
is less than envisaged by the EIS, note that the EIS canvassed the issue
of a land swap that has now been forgotten. The Randwick terminus was
relocated to High St but that did not save High Cross Park entirely.
High Cross Park had been selected for an above-ground power
substation incorporating "driver amenities" with a footprint of 80
square metres and which would probably have been about 3 metres tall
with noisy exhaust fans. However, a 17 September 2015 announcement said
that the "transformer would now be underground" but didn't mention the
$3 million undergrounding cost to be borne by Randwick ratepayers. The
amenities will move to a location in High St near the terminus.
-
Trees lost to light
rail
Including street trees in Devonshire St, Anzac Pde, Alison Rd and Wansey
Rd etc, plus parks, the total loss is well over five hundred trees.
Unfortunately, so many trees will be lost that anyone criticising CSELR on
any ground risks being dismissed as a tree-hugging NIMBY.
-
Olivia Gardens
About 100 residents were evicted by August 2014 and the building was
demolished early in 2015.
-
Parking displaced by
light rail
People are not satisfied by "compensatory" parking to be provided remote
from where they want to park.
-
Noise nuisance
Although it is possible to reduce wheel squeal on curves by treating the
wheels and track, little can be done to reduce rolling rumble noise. This is
likely to be an issue in Devonshire St and Wansey Road.
-
Kingsford shops
Neither of the relevant stops (Strachan St and the Kingsford terminus) is
convenient for most of the existing shops. Strachan St is too far north. The
terminus is too far south - crossing the Nine Ways intersection to get to it
will be a nightmare for pedestrians.
Businesses are concerned about the loss of parking.
-
Electrical
The trams use significant power. Indicative figures for the Gold Coast
light rail system which uses 45-metre trams, are 1250 amps traction current
plus 250 amps for air-conditioning etc, at 700 volts DC. Scaling this up for
67-metre trams suggests about 2000 amps. While full power is only drawn for
short periods of acceleration, each substation has to be capable of
supplying well over a megawatt for each tram in its zone.
None of the above makes wire-free operation a good idea in George St. For
a discussion of the cons of wire-free operation, see page 261 of Transit
Australia, September 2014. The system used by Alstom for wire-free trams
relies on a segmented third rail which is only powered when there is a tram
above it; relying on that may have the disadvantage of precluding trams by
other manufacturers. Also note that the "ugliness" of overhead wiring can
easily be exaggerated by a photographer with a telephoto lens; the wiring
probably won't look as bad as depicted.
Interestingly, the Newcastle light rail service is also wire-free between
stops. But it doesn't use the Alstom system because, according to the
Minister as quoted in
The Newcastle Herald, that system can't be used in Newcastle
"because of the corrosive effects of the sea water".
He didn't explain why Circular Quay
water is less corrosive than Newcastle's.
-
Solution
Simply, make permanent the
interim bus arrangements
that commenced in October 2015. And don't build CSELR.
Better, all of the above problems
could be averted by cancelling CSELR and instead extending the Eastern
Suburbs railway underground from Bondi Junction to Kingsford. There would be
a station servicing UNSW and the PoW hospitals. There could also be a
Charing Cross station.
The question of banning cars from
part of George St is quite separate. It could be done at any time. Or a toll
cordon around the CBD could be implemented to deter cars from entering the
area.
Otherwise,
- Provide track crossovers outside Australia Square so that trams
could be turned back whenever crowds at Circular Quay or traffic
crossing between Bridge and Grosvenor Sts precluded trams from going
further north.
- Similarly, there should be a few crossovers elsewhere along the
route to mitigate the impact of breakdowns or other blockages.
- Put the tracks in a cut-and-cover tunnel under Devonshire St between
the Gaelic Club and about South Dowling St. Dr Gerofi's submission to
the EIS estimated about $100 million for this.
- As suggested by Peter Mills' EIS submission, keep the Randwick trams
on the south side of Alison Rd. Run them round the depot and let them
service the Carlton Street stop, thus balancing loads on the two CSELR
legs. This would facilitate eventual connection to Green Square station.
- Provide grade separation at the Alison/Anzac junction, keeping tram
tracks above the flood level.
- Other locations and configurations should be considered for the
Kingsford terminus. Bunnerong Rd looks more promising than Anzac Pde.
-
Construction costs
A 2011 Legislative Council
inquiry found that NSW construction costs per distance for heavy rail were
high compared with similar projects elsewhere in comparable economies.
According to SMH of 10 November
2014, estimated construction costs have blown out to $2.2 billion. However,
important details such as the length of trams and the frequency of services
were still being negotiated. Despite about forty EIS submissions criticising
the project for lack of capacity, this inability to carry peak-hour loads
acceptably was only admitted on 23 October 2014 when the Minister said "As I
have said previously, the biggest challenge for this project is meeting the
high demand from customers who are expected to choose light rail over buses,
private vehicles and other transport options". So we cannot be sure we are
hearing the full truth.
-
PPP risks
The risk will lie with the NSW government, not the winning tenderers who
will have a guaranteed return.
-
Car-free George St
This could have been implemented
at any time. It is a separate issue from light rail.
-
Buswrap
Many tram windows are covered with perforated advertising film which
becomes translucent in wet weather and obscures the view? See the problems
set out in
Wikipedia.
-
Fudged figures in the
EIS
See Peter Mills' EIS submission and the table notes at the end of Peter
Egan's submission.
-
Benefit/Cost Ratio
It would be very interesting to see details of the calculation of 10000
jobs to be created by the light rail
and also of the claimed $4 billion benefits.
Table of CSELR benefits claimed by T4NSW, from page 6 of the
CSELR Business Case Summary dated November 2013
"Wider economic benefits" may mean agglomeration benefits.
The admitted costs do not include any allowance for disrupting Broadway
and Anzac Bridge bus services nor for reducing passenger amenity in the
eastern suburbs. If they did, the project would be much less attractive and
might well be unwarranted.
The NSW Auditor-General reviewed the claimed business case and reported
in November 2016 - see Later Developments below.
-
Wider effects
The plan is to remove all buses from CSELR's service area, However, that
would leave holes in the present services to some areas. For example, many
of the buses which will be removed use Cleveland St to get from Randwick to
the CBD. What happens to Cleveland St without buses?
-
Upselling
Surprisingly, many people in the south-eastern suburbs still think that
the light rail will supplement their bus services. It won't. Subject to
politics of what is acceptable, bus services will be permanently withdrawn
as far as overcrowding will permit, And many people in the inner western
suburbs don't realise that one day they will be expected to change between
bus and tram at Rawson Place.
The authorities must be aware of this misunderstanding. We can only
assume that they don't propose correcting it until the last minute if at
all.
-
CBD and Devonshire St
shopkeepers
Originally, most George St shopkeepers seemed unconcerned about the
growing disruption and its possible effects on their businesses. The Sydney
Business Chamber asserted its unreserved support for the project. Yet the
Chamber has also
said "we ... need to take action to spread peak demand", presumably by
facilitating increased flexitime which could reduce peak-hour demand for
transport.
But many businesses, especially those which rely on passing trade,
suffered a drastic downturn. This resulted in some staff losing their jobs
and in the closure of some business. The NSW Government is resisting
attempts to extract adequate compensation from it, even though chronic
construction delays maee the pain worse.
Some shopkeepers attended meetings organised to address the matter. The
relief being offered was obviously too little too late.
-
CBD cycleways
The march of CSELR will delay completion of the cycleway network - see
http://www.smh.com.au/nsw/delays-threaten-sydney-cycleways-as-changes-to-castlereagh-street-considered-20141112-11l12e.html
and
http://www.smh.com.au/nsw/bike-lanes-out-as-george-street-light-rail-project-takes-off-20150528-ghbamo.
-
Political
The serviced area outside the CBD almost
coincides with the Randwick local government area, plus the two Sydney high
schools. However, there are serious ramifications for the inner western
suburbs, due to the effect on Broadway and Anzac Bridge bus services.
Relevant state seats in the east are Sydney (independent), Coogee
(Liberal), Maroubra (Labor), Newtown (Green) and perhaps Heffron (Labor). In
the western suburbs, the affected electorates will be Balmain (Green),
Newtown (Green), Summer Hill (Labor) and Drummoyne (Liberal).
Some of the cost of the light rail is being paid by Sydney City Council.
The Sydney local government area includes considerable areas in suburbs like
Glebe and Erskineville and collects rates from those areas. However, the
residents of these areas cannot be said to benefit from the project.
Many politicians think that investment in public transport is a good
idea. However, CSELR isn't about getting passengers out of cars onto
improved public transport services but rather shifting them from one mode of
public transport to another at huge cost. Think of
greenwash.
-
Contract administration
Under the former Goodling administration, innovative tendering was to be
used to minimise construction disruption and to expedite the work. Tenderers
for each piece of work were to stipulate not only their price but also the
number of weeks they would complete the work in. Preference was to be given
to tenderers who would work quickly. There was to be a financial incentive
for keeping to the agreed schedule.
It is very clear that this didn't happen. The prolonged mess in George St
speaks for itself. And trackside residents of Anzac Parade tell stories of
hoardings going up, piles of sand and other materials lying abandoned for
months, and then noisy work running overnight. Complaints about unnecessary
noise were rebuffed by contractors who said they were allowed to work around
the clock and the job was urgent.
-
Later developments
-
Randwick Council was
pressing for the planned Alison Road track to be returned to the south
side of the road west of Darley Road. This would have saved a long stand
of mature trees.
-
Surry Hills residents
were pressing for an additional station at the eastern end of Devonshire
St. They said that the Ward Park stop is too far away from the Wimbo
Park area and there should be a station near the Olivia Gardens site.
-
The depot site at
Randwick has been found to contain a large quantity of indigenous
artefacts and there have been calls to cease work to allow proper
investigation.
Learn more...
-
Questions have been
raised about the effects that developments on the Inglis site will have
on road traffic in the Barker St area, particularly when High St is lost
to light rail.
Learn more...
-
Authorities have asked
businesses to spread working hours, so that each peak period stretches
over four hours, to mitigate congestion due to construction works.
Learn more... No doubt the request will be renewed when construction
finishes and operation begins.
-
The question of bus
operation along the tram routes at night and during repairs etc. has
re-surfaced Several of the stops are centre-island and are not suitable
for use by buses.
Learn more...
-
Several changes are to be
made to bus services from 20 August 2016. Some Anzac Pde bus stops will
be removed permanently, increasing some passengers' walking by up to 260
metres. Six bus stops will be removed from Cleveland St. These changes
are claimed to "simplify" the bus network. Quite.
-
A number of northside bus
services are to be altered from 5 September 2016. Instead of terminating
in the CBD, they will end at North Sydney. This is likely to be
inconvenient for passengers from many areas, particularly suburbs like
Riverview which don't have alternative transport. The change would
appear to be due to a squeeze on bus space in the CBD to allow for light
rail.
-
Three medium-rise
residential buildings in High St will require access from Arthur Street
because the light rail stop in High Street will obstruct their frontage.
Land to be taken for the access will deprive a childcare centre of its
garden.
-
Dr Mehreen Faruqi, the
Greens MLC, moved in September 2016 for a select committee inquiry into
the project. Although supported by Labor, her motion was opposed by
Shooters & Fishers and the Christian Democrats and hence the motion was
lost.
-
In November 2016, Clover
Moore wrote to the Premier requesting that the impact of CSELR on George
St be restrained.
-
The NSW Auditor-General
released a
performance audit on the project at the end of November 2016.
Surprisingly, although quite scathing about many matters, the audit did
not dwell on the trams' lack of carrying capacity. Premier and former
transport minister Gladys Berejiklian has not explained when she became
aware of a construction cost blowout nor why she did not inform the
public of the correct reason for the blowout. One wonders whether and
when she ever realised she was building an expensive transport system
that would be incapable of meeting its core requirement.
-
In June 2017 an expansion
of the medical facilities in High St including re-development of the
land between the hospital and the university was announced. The
announcement did not discuss how the extra traffic generated would be
handled by the roads system nor how extra passengers would be
accommodated on CSELR services.
-
In July 2017, it emerged
that CSELR trams and IWLR trams differ on a range of measures,
particularly wheel profile, and hence aren't interoperable.
Learn more... The different standards are apparently because the
western part of the IWLR track was once planned to be shared with
freight trains.
-
Early in August 2017, it
was reported that NSW Transport Minister Andrew Constance and NSW Small
Business Minister and Deputy Premier John Barilaro were working together
to develop a number of financial assistance measures for those impacted
by light rail construction. On 23 August businesses were told that rent
relief is to be available.
-
In October 2017, The
Australian obtained a document confirming that transport authorities
had long been aware of the inadequate capacity of the light rail system.
Learn more....
-
In December 2017, the NSW
Opposition obtained a document showing that boosting property values
around the route was a key performance indicator for the light rail
system.
Learn more...
-
In the Southern
Courier of 27 March 2018, Meriton developer Harry Triguboff was
quoted as willing to negotiate with the NSW Government to help fund
light rail to Pagewood Green, a new residential tower near Eastgardens
shopping mall. How the light rail might connect to the Kingsford
terminus of CSELR was not indicated. Unfortunately, there will be no
spare capacity on the light rail north of Alison Road and won't be
unless and until a second northern terminus is constructed. Possible
terminus sites include Bondi Junction, Edgecliff, Kings Cross,
Darlinghurst, St James, Green Square, Redfern ... Without a second
northern destination for trams, extensions at the southern ends would be
ill-advised because they would worsen peak-hour overcrowding.
-
According to the
Weekend Australian of 7 April 2018, contractor Acciona is demanding
an extra $1.2 billion from T4NSW. The matter reached the N.S.W. Supreme
Court, with the first hearing on 13 April 2018. The only certainty is
that completion of the light rail will be delayed and subject to massive
cost over-runs.
-
A second dispute (but
much smaller - only $4 million) reached the Federal Court. A
subcontractor claims T4NSW did not make clear that old tram tracks lay
under George St and nor did T4NSW allow enough hours of access to the
site for trenching work to be done.
-
We understand that
metrobuses M10 and M50 will no longer serve the south-eastern suburbs
once the light rail is running. Currently they go to Randwick and
Maroubra Junction respectively. Anyone who uses those to travel through
the CBD won't be happy.
-
On 25 January 2019, the
Legislative Council committee
inquiry released its final report. While numerous issues with
construction disruption are noted, little emphasis is put on
passenger-carrying capacity of the light rail. Worse, Government members
of the Committee voted en bloc against all motions which might
have embarrassed the government; as a result, the report is much blander
and less probing than it should have been.
-
On 3 June 2019, it
emerged that T4NSW had reached a $576M settlement of the suit brought by
the constructing consortium and its Spanish contractor. The suit alleged
failure of T4NSW to advise that it had not agreed treatment of certain
underground power lines with Ausgrid; the construction was thereby made
costlier and slower.
-
During testing in
Randwick in July and August 2019, it was noted that the new traffic
signals in High St at the Hospital Road intersection stopped some
inbound trams. The rear of those trams did not clear the ambulance
access to the Childrens Hospital. One hopes that traffic signal priority
can be used to prevent such interference.
-
It became known in
November 2019 that CSELR trams would be available for all-over wrap
advertising, despite the
constraints this imposes on passengers' views in wet weather and at
night.
Learn more...
-
When the Kingsford L3
line opened, timetables showed that only 12 trams per hour each way were
to run along George St. That means a tram every 10 minutes each way to
Randwick and Kingsford. So the maximum capacity each way is only about
12 times 450 = 5400 passengers per hour, which is certainly not enough
for normal operation.
-
No progress here
Despite recognition from many quarters that the light rail's capacity
will not be adequate for peak hour, no admission has ever been made by
Transport for NSW and/or the ministry that there is a problem and that
solutions should be sought. It would be worthwhile seeking a second northern
terminus for the line to supplement George St. Possibilities such as Bondi
Junction, Kings Cross, St James, Green Square and/or Redfern/Darlington
should be evaluated. Unfortunately, there is no indication that any such
investigation is in progress.